Harvard Avenue Improvement Project (Jefferson Park to Plymouth)

General Information

Project Location(s):
North Harvard Avenue from Jefferson Park to Plymouth Street
Project Status:
Construction
Bid Opening Date:
Tuesday, December 15, 2020, 11:00 A.M., via Zoom
Mandatory Pre Bid Meeting:
Tuesday, December 8, 2020, 11:00 A.M., via Zoom
QuestCDN Number:
7417121
Construction Start Date:
Spring 2021
Construction Completion Date:
2021
Contractor:
Builders Paving, LLC
Construction Engineer:
Engineering Enterprises, Inc.
Design Engineer:
Christopher B. Burke Engineering, Ltd.
Awarded Contract Amount:
$1,048,000.00
Adjusted Final Contract Amount:
TBD
Funding Source(s):
GO Bonds, Wastewater Fund, IEPA Water Loan

Objective

To improve the condition of the roadway by means of selected pavement rehabilitation methods. To improve the water system capacity and reliability by replacing the existing undersized water main.

Description

This project consists of improvements on North Harvard Avenue from Jefferson Park to Plymouth Street. The project consists of installing approximately 1,800 linear feet of 8” water main, including fire hydrants, valves and water services. The project also includes pavement removal, aggregate base course, Hot-Mix Asphalt Binder Course, Hot-Mix Asphalt Surface Course, curb and gutter installation, sidewalk removal and replacement, driveway pavement removal and replacement, adjusting sanitary services, storm sewer removal and replacement and parkway restoration.  

Justification

The Village’s Pavement Management Program has determined that the condition of the street has deteriorated to the point that pavement rehabilitation is needed. The pavement improvements are to be partially funded by voter approved bond proceeds. The existing 4" water main has insufficient capacity and a high incidence of water main breaks. The Illinois EPA Public Water Supply Loan Program (PWSLP) is expected to provide loan funding for the water main improvements.

Bidding & Planholders  Information

A mandatory pre-bid meeting for contractors interested will be held on December 8, 2020 at 11:00 a.m. via Zoom. Village and Consulting engineering staff will be on hand to answer questions regarding interpretations of the project plans and specifications and discuss project scheduling. If required, a project addendum will be prepared based upon questions raised by the bidding community and distributed to all attendees for inclusion within their respective bids. It will be the Village’s decision whether bids are opened from Contractors that do not attend the mandatory pre-bid meeting.  The mandatory pre-bid Zoom meeting can accessed using the information below:

Scheduled Mandatory Pre-Bid Zoom Meeting 

Meeting ID: 991 6808 8044

Passcode: 348526

Separate proposals for the HARVARD AVENUE IMPROVEMENTS (JEFFERSON PARK TO PLYMOUTH STREET) will be received electronically by the Village of Villa Park, Illinois, at the website www.questcdn.com (QuestCDN #7417121), until the Bid Deadline. Immediately thereafter, the proposals will be read aloud via Zoom. Notwithstanding the foregoing, the Village reserves the right to defer, postpone, delay, or reschedule the Bid Opening for such time and to such date as the Village, in its sole discretion, determines is in the best interest of the Village. The Bid Opening Zoom Meeting can be accessed using the information below:

Scheduled Bid Opening Zoom Meeting

Meeting ID: 952 9481 7752

Passcode: 210713

Proposals shall be submitted in accordance with the Bidding Documents prepared by Christopher B. Burke Engineering, Ltd., 9575 W. Higgins Road, Rosemont, IL 60018.

Minority and Women Owned Businesses (MBE/WBE) are encouraged to submit bids on this project. Federal Labor Standards, Prevailing Wage Rates, and Section 3 regulations apply to this Project.


Project Updates

Date
Description
April 2, 2021A contract was executed this week. Preliminary work has already started, and full construction operations are expected to start next week.
March 26, 2021Staff is coordinating the execution of contracts and the start of construction. Construction is expected to begin in the next one to two weeks.
March 19, 2021A pre-construction meeting was held this week. Staff is now coordinating the execution of contracts and the start of construction. Construction is expected to begin in the next two to three weeks.
March 10, 2020A contract was awarded with Builders Paving, LLC, at the the March 8, 2021 Village Board meeting. A preconstruction meeting is scheduled.
January 26, 2021A bid opening for this project was held in December. Staff is working through the contractor approval process required as a part of the CDBG grant funding awarded to the project, and expects to submit a contract award recommendation for board consideration when that process is complete.
January 15, 2021Distribution of payment letters for residents who expressed interest in optional work has begun this week. Residents have until Monday, March 1, 2021, to submit any payments for optional work.
December 30, 2020The submittal period for resident questionnaires has ended.
December 15, 2020A bid opening was held on December 15, 2020, via Zoom. Staff is in the process of reviewing the bids. The apparent low bidder is Builders Paving, LLC, of Hillside, IL.
December 11, 2020Addendum #03 was issued.
December 8, 2020A mandatory pre-bid was held via Zoom. A number of contractors attended. The bid opening is still scheduled for Tuesday, December 15, 2020, at 11:00 a.m.
December 4, 2020Addendum #02 was issued. Questionnaires for optional work were delivered to residents within the project area.
November 17, 2020Addendum #01 was issued. The QuestCDN project number has changed from #7279465 to #7417121.
November 13, 2020The project was advertised for bidding.
September 30, 2020A progress meeting was held with DuPage County Community Development Commission and Christopher B. Burke Engineering, Ltd. The pre-final plans and specs are expected soon, and the advertisement for bids is expected to be issued within the next few months.