Jackson Pond Expansion Project
General Information
Project Location(s): | Jackson Pond at Jackson Middle School |
---|---|
Project Status: | Final Design Engineering |
Bid Opening Date: | 2022 |
Construction Start Date: | TBD |
Construction Completion Date: | TBD |
Contractor: | TBD |
Construction Engineer: | TBD |
Design Engineer: | V3 Companies of Illinois, Ltd. |
Awarded Contract Amount: | TBD |
Adjusted Final Contract Amount: | TBD |
Funding Source(s): | Stormwater Fund, PDM Grant |
This project is a portion of the larger Sugar Creek Watershed Drainage Improvement Project. This project also includes:
- Michigan Avenue Improvement Project (Madison to Jackson)
- Jackson Pond Overflow Project
- Jackson Pond Outlet Project
More detailed information on these projects can be found on their respective project pages.
Objective
To expand the Jackson Pond Stormwater Detention Basin to lessen the frequency and severity of area flooding.
Description
This project consists of the expansion of the Jackson Pond stormwater basin at Jackson Middle School.
Justification
The expansion of the Jackson Pond stormwater detention basin was proposed by the 2015 Sugar Creek Watershed Drainage Improvement Project Conceptual Design Report prepared by V3 Companies of Illinois.
Bidding Documents
Contract Documents
Project Updates
Date | Description |
---|---|
May 6, 2022 | Engineering design of this project is in progress. Staff has held several design progress meetings with the design engineer. Staff has also conducted a partial site walkthrough with the design engineer, and others are anticipated in the near future. Staff has also received preliminary plans for the expansion to the existing pond, and is now working to review that submittal. |
February 4, 2022 | Topographic surveying for this project is still in progress. The surveying efforts are expected to be completed in several phases due to the size of the project area. Staff has held several design progress meetings with the design engineer. |
January 14, 2022 | Topographic surveying for this project is in progress. |
December 20, 2021 | Topographic surveying for final design on the project began this week. This surveying will include a drone which will capture aerial imagery and terrain elevations via LIDAR. The surveying efforts are expected to be completed in several phases due to the size of the project area. Staff also held a kick-off meeting this week for Phase 2 design engineering of the project. |
December 10, 2021 | A proposed engineering services agreement for final design of the project has been submitted for consideration at the December 13, 2021 Village Board meeting. |
November 19, 2021 | Staff is working to initiate the grant project with IEMA and to negotiate a proposed engineering services agreement for final design of the project. |
October 29, 2021 | The total estimated cost of the project is approximately $5.8 million. A grant agreement with the Illinois Emergency Management Agency (IEMA) has been fully executed. Staff is now working to initiate the grant project with IEMA. |
October 15, 2021 | The total estimated cost of the project is approximately $5.8 million. A grant agreement with the Illinois Emergency Management Agency (IEMA) was approved at the October 11, 2021 Village Board meeting. |
September 24, 2021 | The Village has been awarded grant funding of $4,000,000 for this project through the Federal Emergency Management Agency’s Pre-Disaster Mitigation (PDM) Grant Program. Staff is awaiting information from FEMA regarding the timetable for the grant process. |
June 11, 2021 | Staff has responded to a request from IEMA for additional information needed for the evaluation of the village’s pending application for FEMA grant funding for this project. Staff is still awaiting a decision from FEMA regarding that application. The engineering design of the pond expansion is complete, but the project has not been able to proceed to construction due to a lack of funding. Staff is developing alternate options for construction. |
May 28, 2021 | Staff is still awaiting a decision from FEMA regarding the application. |
April 2, 2021 | Staff has responded to a request from IEMA for additional information needed for the evaluation of the village’s pending application for FEMA grant funding for this project. Staff is still awaiting a decision from FEMA regarding that application. |
January 1, 2021 | Engineering design of the pond expansion is complete, but the project has not been able to proceed to construction due to concerns from School District 45. Staff is developing alternate options for construction and awaiting a decision from FEMA regarding the village’s pending grant application. |
December 4, 2020 | Staff is developing alternate options for construction and awaiting a decision from FEMA regarding the village’s pending grant application. |
September 11, 2020 | Engineering design of the pond expansion is complete, but the project has not been able to proceed to construction due to concerns from School District 45. Staff is preparing a joint application with the County for FEMA funding along with developing alternate options for construction. |
September 4, 2020 | Engineering design of the pond expansion is complete, but the project has not been able to proceed to construction due to concerns from School District 45. In addition to affecting the project timeline, those concerns have also resulted in significantly higher estimates for construction costs. In response, staff has been actively seeking out external funding sources and submitting funding applications. |
May 22, 2020 | Engineering design of the pond expansion is complete, but the project has not been able to proceed to construction due to concerns from School District 45. In addition to affecting the project timeline, those concerns have also resulted in significantly higher estimates for construction costs. In response, staff has been actively seeking out external funding sources and submitting funding applications. Staff submitted another such grant application this week to the Rebuild Illinois Fast Track Program that was announced by Governor Pritzker last week. Staff is optimistic about the application’s chances and hopes to receive a decision on whether or not the project will receive funding by the end of June. Separately from the pond expansion efforts, design of the upstream stormwater improvements on Wisconsin and Addison is still in the planning stages. Staff is working with the prospective design engineer to establish the scope of those design efforts. |
April 18, 2019 | The project is currently in the planning stages. Staff is working with the prospective design engineering consultant to establish the scope of design efforts. |
Contact Us
-
Michael Guerra, P.E.
Public Works Director
Email the Engineering Division
Online Contact Form
Staff Directory
Office Address
Public Works Department
11 West Home Avenue
Villa Park, Illinois 60181
Mailing Address
Public Works Department
20 South Ardmore Avenue
Villa Park, Illinois 60181
Ph: 630-834-8505
Fx: 630-834-8509
Emergency: 630-834-7447
Hours
Monday through Friday
7:30 a.m. to 4:00 p.m.