2018 Pavement Markings Program
General Information
Project Location(s): | Various (see map) |
---|---|
Project Status: | Complete |
Bid Opening Date: | Completed through the Municipal Purchasing Cooperative |
Construction Start Date: | Fall 2018 |
Construction Completion Date: | Spring 2019 |
Contractor: | Superior Road Striping, Inc. |
Construction Engineer: | In-House |
Design Engineer: | In-House |
Awarded Contract Amount: | $51,489.10 |
Adjusted Final Contract Amount: | $50,466.45 |
Funding Source(s): | Street Improvement Fund |
OBJECTIVE
To apply, refinish, and update to the most current standards road lines, markings, and symbols throughout the village.
DESCRIPTION
This project consists of the application of thermoplastic and modified urethane striping to asphalt and concrete pavement throughout the village.
JUSTIFICATION
Several major roads throughout the Village of Villa Park are in need of new road markings due to wear and tear over time from passing traffic. Additionally, the standard for certain types of road markings has potentially changed since the last time they were applied, and need to be updated. The reapplication of striping is periodic maintenance that is required to keep roads in safe condition.
Bidding Documents
Contract Documents
Related Documents
PLANHOLDERS
Organization | Organization Address |
---|---|
Superior Road Striping, Inc. | 1980 North Hawthorne Avenue Melrose Park, IL 60160 |
PROJECT UPDATES
Posted Date | Description |
---|---|
September 13, 2019 | All work is complete. A final balancing change order has been approved and staff has processed final payment to the contractor. This project is now closed. |
September 6, 2019 | All work is complete. A final balancing change order has been approved. Staff is processing final payment to the contractor and working to close out the project. |
August 15, 2019 | Staff has submitted a proposed final balancing change order for Village Board consideration. |
August 2, 2019 | All work is complete. Staff is working to close out the contract. |
July 26, 2019 | Pavement markings on concrete streets adjacent to north Avenue were completed this week. |
June 6, 2019 | Work is in progress. Pavement markings on concrete streets adjacent to North Avenue are pending. |
May 23, 2019 | Work resumed this week. Pavement markings are being placed on concrete streets adjacent to North Avenue. |
March 28, 2019 | Staff is working with the contractor to coordinate the restart of work. |
December 13, 2018 | Due to weather, no additional work is expected this year. |
November 8, 2018 | Striping on streets adjacent to North Avenue is expected to begin within the next few weeks. |
November 1, 2018 | Striping work on St. Charles Road was completed this week. Striping on streets adjacent to North Avenue is expected in the next few weeks. |
October 18, 2018 | Construction is expected to begin in late October |
October 11, 2018 | A pre-construction meeting was held on October 9, 2018. Construction is expected to begin next week. |
October 4, 2018 | A pre-construction meeting is scheduled for October 9, 2018. |
September 27, 2018 | Staff is working to schedule a pre-construction meeting with the contractor. |
September 13, 2018 | Staff has obtained pricing for thermoplastic striping (for asphalt streets) through the Suburban Purchasing Cooperative and requested pricing for modified urethane striping (for concrete streets). The low bidder for the cooperative was Superior Road Striping, Inc. Staff will present a contract to the Board for consideration at the September 24, 2018 Board Meeting. |
Contact Us
-
Michael Guerra, P.E.
Public Works Director
Email the Engineering Division
Online Contact Form
Staff Directory
Office Address
Public Works Department
11 West Home Avenue
Villa Park, Illinois 60181
Mailing Address
Public Works Department
20 South Ardmore Avenue
Villa Park, Illinois 60181
Ph: 630-834-8505
Fx: 630-834-8509
Emergency: 630-834-7447
Hours
Monday through Friday
7:30 a.m. to 4:00 p.m.