Jackson Pond Outlet Project
GENERAL INFORMATION
Project Location(s): | Jackson Pond and Willowcrest Subdivision |
---|---|
Project Status: | Complete |
Bid Opening Date: | February 12, 2019 |
Construction Start Date: | April 1, 2019 |
Construction Completion Date: | Summer 2019 |
Contractor: | EarthWerks Land Improvement and Development Corp. |
Construction Engineer: | Christopher B. Burke Engineering, Ltd. |
Design Engineer: | V3 Companies of Illinois, Ltd. |
Awarded Contract Amount: | $305,718.00 |
Adjusted Final Contract Amount: | $305,601.85 |
Funding Source(s): | Stormwater Fund |
This project is a portion of the larger Sugar Creek Watershed Drainage Improvement Project. This project includes:
- Michigan Avenue Improvement Project (Madison to Jackson) (2018)
- Jackson Pond Overflow Project (2019)
- Jackson Pond Outlet Project (2019)
- Jackson Pond Expansion Project (2022)
- Jackson Area Improvement Project (2023)
More detailed information on these projects can be found on their respective project pages.
OBJECTIVE
To expand the Jackson Pond stormwater detention basin to lessen the frequency and severity of area flooding. The stormwater improvements are a portion of a larger project identified in the Sugar Creek Basin Flood Control Study.
DESCRIPTION
The project consists of the construction of approximately 1,100 feet of storm sewer beginning at Jackson Pond and connecting to existing storm sewers along Willow Crest Drive. The project includes the construction of new storm sewer within Village-owned property and along Leslie Lane and Willow Crest Drive.
JUSTIFICATION
This project is to be partially funded by voter approved bond proceeds. The storm sewer is proposed in the V3 Flood Control Study. The Jackson Pond expansion is proposed in the V3 Flood Control Study.
Bidding Documents
Contract Documents
Planholders
Organization | Organization Address | Planholder | Addendum #01 Received |
---|---|---|---|
Misfits Construction Co. | 223 S Wacker Dr, Ste. 8400 Chicago, IL 60606 | Yes | |
Archon Construction Co., Inc. | 563 S Rte 53 Addison, IL 60101 | Yes | |
H. Linden and Sons Sewer and Water, Inc. | 722 E South St Plano, IL 60545 | Yes | Yes |
Cerniglia Co. | 3421 W Lake St Melrose Park, IL 60160 | Yes | |
EarthWerks Land Improvement and Development Corp. | 1240 Lyon Rd Batavia, IL 60510 | Yes | Yes |
Martam Construction, Inc. | 1200 Gasket Dr Elgin, IL 60120 | Yes | Yes |
LIFCO Construction, Inc. | P.O. Box 87200 Carol Stream, IL 60188 | Yes | |
Trine Construction Corp. | 1S420 Schaffner Rd Wheaton, IL 60189 | Yes | |
John Neri Construction Co. | 770 Factory Rd Addison, IL 60101 | Yes | Yes |
Copenhaver Construction, Inc. | 75 Koppie Dr Gilberts, IL 60136 | Yes | Yes |
A Lamp Concrete Contractors, Inc. | 1900 Wright Blvd Schaumburg, IL 60193 | Yes | Yes |
Landmark Contractors, Inc. | 11916 W Main St, P.O. Box 1104 Huntley, IL 60142 | Yes | |
Swallow Construction Corp. | 4250 Lacey Rd Downers Grove, IL 60515 | Yes | Yes |
PROJECT UPDATES
Posted Date | Description |
---|---|
December 20, 2019 | All work is complete. Staff has processed final payment to the contractor. This project is now closed. |
November 1, 2019 | All site work is complete. Staff has submitted a proposed final balancing change order to the Village Board for consideration at the November 11, 2019 board meeting. |
October 18, 2019 | Only punch list work remains. Staff is working with the contractor to coordinate its completion. Staff also expects to submit a proposed final, balancing change order to the Village Board for consideration at the November 11, 2019 board meeting. |
July 11, 2019 | Staff has provided the contractor with a punch list. |
June 28, 2019 | Construction of the new storm sewer is complete. Staff is preparing a punch list for the project. |
May 3, 2019 | Construction of the new storm sewer is complete. Restoration work is now in progress. |
April 25, 2019 | Construction of the new storm sewer was completed this week. Restoration work is now commencing. |
April 18, 2019 | Construction of the new storm sewer is currently in progress. This work is expected to be completed within the next week. |
April 11, 2019 | Construction of this started last week. Construction of the new storm sewer is currently in progress. |
March 28, 2019 | Contracts for this project were executed this week. Staff is now working to schedule a pre-construction meeting. |
March 21, 2019 | A construction contract and construction engineering agreement for this project were awarded at the Village Board meeting on February 25, 2019. Staff is now working to execute contracts. |
March 8, 2019 | The South Michigan and Jackson Pond Project page was split into three different pages, Michigan (Madsion to Jackson), Jackson Pond Overflow Project, and the Jackson Pond Outlet Project. |
February 28, 2019 | A construction contract and construction engineering agreement for this project were awarded at the village board meeting on February 25, 2019. Staff is now working to execute contracts. |
February 14, 2019 | A bid opening was held on February 12, 2019, at 10:00 a.m. The Village received ten bids. The apparent low bidder was EarthWerks Land Improvement and Development Corporation of Batavia, Illinois, with an as-read bid amount of $305,718.00. Staff has submitted a contract award recommendation for board consideration. |
January 31, 2019 | The project is current advertised for bidding. |
January 25, 2019 | The Jackson Pond Outlet Project was advertised. The bid opening is Tuesday February 12, 2019, at 10:00 a.m. |
January 3, 2019 | Construction is expected to begin in early 2019. |
December 13, 2018 | Construction is expected to begin in January. |
December 6, 2018 | A preconstruction meeting was held on December 4, 2018. The contractor expects to begin work in January. |
November 29, 2018 | A preconstruction meeting for Jackson Pond is scheduled for December 4, 2018. |
November 8, 2018 | Staff met with the County to discuss stormwater modeling and issues with School District 45. |
November 1, 2018 | A bid opening for the overflow basin was held on November 1, 2018. Staff plans to submit a recommendation to the Board at the November 26, 2018 Board Meeting. |
October 29, 2018 | A second addendum was issued for Jackson Pond. The bid opening has been rescheduled for November 1, 2018. |
October 25, 2018 | Michigan Avenue: a final balancing change order was approved by the Board on October 22, 2018 and Staff is working to close out the project. |
October 18, 2018 | A bid opening for the overflow basin is scheduled for October 30, 2018. District 45 has notified the Village that they do not wish to allow any spoil from the expansion of Jackson Pond, including that which is generated from District 45 property, on District 45 property. |
October 11, 2018 | Michigan Avenue: a final balancing change order will be presented to the Board at the October 22, 2018 Board Meeting. Jackson Pond: Staff has received County approval to bid the project. A bid opening is scheduled for Tuesday, October 30th, 2018 at 10:00 a.m.. A mandatory pre-bid meeting is scheduled for Tuesday, October 23, 2018 at 10:00 a.m. The village is awaiting a response from District 45 about work on District 45 property. |
October 4, 2018 | Staff is waiting for final approval before going out to bid for Jackson Pond. The Village provided responses to questions from District 45 about the Jackson Pond construction project. |
September 20, 2018 | Staff provided review comments to the consultant for Jackson Pond. The village received questions from District 45 about the construction on their property and Staff is working to address those questions. |
September 13, 2018 | The design of the overflow basin continues. |
September 6, 2018 | A meeting with ComEd was held to determine how power could be extended through the Jackson Pond project area. |
August 17, 2018 | The consultant is working to complete design of the overflow basin for Jackson Pond. |
August 10, 2018 | A response has been submitted to IEMA for a potential grant for Jackson Pond. |
July 27, 2018 | Staff received requests for additional information for both CDBG and IEMA for the Jackson Pond grants, and is working to address those requests. |
July 19, 2018 | A final balancing change order for Michigan Avenue will be submitted to the Board at an upcoming board meeting. |
July 5, 2018 | Revised grant paperwork for Jackson Pond was submitted to CDBG and IEMA at their request for two separate grants. |
June 7, 2018 | All work except for the punch list on Michigan Avenue is complete. The consultant is working to address Staff comments on Jackson Pond. |
June 1, 2018 | On Michigan Avenue, the HMA surface was installed. All work except for the punch list is now complete. |
May 24, 2018 | Due to weather end the end of school, HMA surface was unable to be installed. HMA surface is expected to be installed next week. |
May 17, 2018 | On Michigan Avenue, the HMA binder has been installed as well as the sod. HMA surface is expected to begin the week of May 21, 2018. |
May 10, 2018 | On Michigan Avenue, excavation of the pavement is complete. The HMA binder will be installed next week, weather permitting. The design consultant is working to complete plans and specs for Jackson Pond. |
May 3, 2018 | All concrete work is complete on Michigan Avenue. Removal of the existing pavement has begun. V3 Companies is working to complete Phase II design for Jackson Pond. Staff is working with V3 Companies to provide DuPage County with Grant requirements. |
April 26, 2018 | Underground work and concrete removal is complete on Michigan Avenue. Concrete replacement is expected to be complete the week of April 30th. Staff is working with V3 Companies to provide DuPage County staff with grant requirements, and with State Hazard Mitigation Department to respond to questions about possible additional funding for future phases. |
April 19, 2018 | On Michigan Avenue, the installation of all storm sewers is nearly complete. Sanitary service and lead water service replacements will follow. Staff met with CDBG staff to discuss CDBG scheduling and funding for Jackson Pond. |
April 12, 2018 | On Michigan Avenue, installation of the 72'' diameter storm sewer is complete and installation of other storm structures has begun. |
April 5, 2018 | On Michigan Avenue, installation of the 72'' diameter sewer continues. The design engineer is working to address comments and complete plans and specs for Jackson Pond. |
March 29, 2018 | On Michigan Avenue, Concrete work at the entrance to Jackson Middle School has been completed. A preliminary review of the Jackson Pond expansion was completed and comments were provided to the designer. |
March 22, 2018 | On Michigan Avenue, installation of the 72'' diameter sewer continues. A meeting with District 45 staff was held to discuss the expansion of Jackson Pond. |
March 15, 2018 | On Michigan Avenue, Installation of the 72'' diameter sewer began this week. Public works and the Police Department assisted with traffic flow around Jackson Middle School while the intersection of Jackson and Michigan was closed for construction. The design engineer is working on Plans and Specs for Jackson Pond. |
March 8, 2018 | On Michigan Avenue, tree removal was completed. Installation of the storm sewer is expected to begin next week. Staff provided comments of preliminary Plans for the Jackson Pond Improvements to the consultant. |
March 1, 2018 | A meeting to discuss the start of the South Michigan improvements is scheduled for March 2, 2018. Staff began review of the preliminary plans for the Jackson Pond Improvements. |
February 22, 2018 | South Michigan improvements will begin when weather permits. Staff is reviewing soils testing results from the fields around Jackson Pond. |
February 15, 2018 | School District 45 has approved the detour plan for the intersection of Jackson and Michigan. The Village has received preliminary plans for the Jackson Pond Improvements. |
February 1, 2018 | A meeting was held with School District 45 staff to discuss the project. |
January 25, 2018 | The design engineer is working on plans and specifications for Jackson Pond. |
January 18, 2018 | A meeting to discuss design concerns of Jackson Pond was held on January 16, 2018. |
January 4, 2018 | A meeting to discuss construction on Michigan has been scheduled with School District 45 for January 26, 2018. |
December 21, 2017 | A pre-construction meeting was held and construction will begin when weather permits (likely in March). |
December 7, 2017 | A construction engineering services agreement for the Michigan Project was approved at the Board Meeting on December 4, 2017. |
November 22, 2017 | A proposal for Phase III construction engineering services for the Michigan Project is expected to be submitted for consideration at the Board Meeting on December 4, 2017. |
November 16, 2017 | A construction contract for the Michigan Project was awarded to A Lamp Concrete Contractors, Inc., at the November 13, 2017 Village Board meeting. Staff is working to execute contracts. |
November 2, 2017 | The bid opening for Michigan was held on October 31. A Lamp was the apparent low bidder. Staff will prepare a recommendation for the board to consider at the November 13 Board Meeting. Soil borings for the expansion of Jackson Pond were performed on November 2, 2017. The results will be analyzed and incorporated into the design. |
October 26, 2017 | Soil borings for the expansion of Jackson Pond are scheduled for November 2, 2017. |
October 19, 2017 | District 45 has approved the IGA between District 45 and the Village for the proposed improvements Staff will present the IGA to the Board for consideration at the October 23 Board Meeting. |
October 12, 2017 | A project kickoff meeting for Phase II Design Engineering was held on October 10, 2017. Once District 45 approves the IGA between District 45 and the Village for the proposed improvements Staff will present the IGA to the Board for consideration. |
October 5, 2017 | Due to a large number of questions the bid opening has been rescheduled for October 31, 2017 to allow staff to provide answers to all potential bidders. A project kickoff meeting for Phase II Design Engineering is scheduled for October 10, 2017. |
September 28, 2017 | Staff will be attending the District 45 Board Meeting on October 2, 2017 to discuss questions about the project. Staff hopes to receive approval from District 45 on the IGA shortly after the questions are answered. The IGA will be presented to the Board for consideration when District 45 is ready. Staff is working to setup a project kickoff meeting for Phase II Design Engineering. |
September 22, 2017 | The portion of the project on Michigan will be advertised on September 22, 2017. A bid opening is scheduled for October 10, 2017. |
September 15, 2017 | Staff received a proposal to complete Phase II design engineering of Jackson Pond from V3. Staff plans to submit the agreement to the Board for consideration at the September 25, 2017 Board Meeting. |
September 8, 2017 | District 45 provided comments on the IGA for Jackson Pond. Staff found them to be mostly acceptable and hopes to have the final version completed soon. |
August 11, 2017 | An IGA was submitted to District 45 to review for the proposed improvements. |
August 4, 2017 | Staff reviewed pre-final Plans and Specs and returned them to the consultant. |
July 14, 2017 | Staff is working to create an IGA with District 45 for the stormwater improvements associated with Jackson Pond. |
June 9, 2017 | Consultant is working to complete Phase II Plans and Specs. A meeting with School District 45 Board is scheduled for June 19, 2017. |
May 12, 2017 | Staff met and discussed various options for the configuration of Jackson Pond and nearby recreational facilities. The consultant is making changes to the design to address staff's concerns. |
April 21, 2017 | Staff and the consultant are discussing various options to try and reduce the footprint of the pond and how those changes would effect cost. |
April 14, 2017 | A meeting to discuss the improvements with Jackson Middle School was held on April 12, 2017. Staff will present the conceptual plans to the School Board on May 15, 2017. |
April 7, 2017 | A meeting to discuss the improvement with Jackson Middle School is scheduled for April 12, 2017. |
March 31, 2017 | Consultant is working to prepare Phase II Plans and Specs. |
March 24, 2017 | Staff provided comments on a preliminary set of Plans. |
February 24, 2017 | The Consultant is works to prepare Plans and Specs. |
February 17, 2017 | The Village met with the consultant to discuss possible options for the outlet and overflow of Jackson Pond. |
February 10, 2017 | The Village attended a meeting with School District 88 to try and gain support for the watershed plan, including Jackson Pond. |
January 20, 2017 | Consultant is working to prepare Phase II Plans and Specs. |
Contact Us
-
Michael Guerra, P.E.
Public Works Director
Email the Engineering Division
Online Contact Form
Staff Directory
Office Address
Public Works Department
11 West Home Avenue
Villa Park, Illinois 60181
Mailing Address
Public Works Department
20 South Ardmore Avenue
Villa Park, Illinois 60181
Ph: 630-834-8505
Fx: 630-834-8509
Emergency: 630-834-7447
Hours
Monday through Friday
7:30 a.m. to 4:00 p.m.