- Home
- Government
- Departments
- Public Works Department
- Engineering Division
- Construction Projects
- Completed Projects
- Completed Projects 2020
- Michigan Avenue (Kenilworth to Central)
Michigan Avenue Improvement Project (Kenilworth to Central)
GENERAL INFORMATION
OBJECTIVE
To improve the condition of the roadway and utilities by means of reconstruction of the existing roadway and separation of the combined sewer system.
DESCRIPTION
This project consists of pavement improvements on South Michigan Avenue from Central Boulevard to Kenilworth Avenue and the separation of the existing combined sewer main.
JUSTIFICATION
The Village’s pavement management program has determined that the condition of the street has deteriorated to the point that pavement reconstruction is needed. The sewer separation was identified by the CBBEL flood control study, and will help alleviate stormwater issues. This project is to be partially funded by voter approved bond proceeds.
BIDDING INFORMATION
The Bidding Documents must be obtained electronically at www.questcdn.com for a non-refundable fee of thirty dollars ($30.00). The documents may be downloaded by entering Quest Project Number #6968271 on www.questcdn.com. A “Not for Bid” hard copy of the documents will be on file for inspection at the office of the Village of Villa Park Public Works Department, 11 West Home Avenue, Villa Park, Illinois, 60181.
Bidding Documents
Contract Documents
Related Documents
- Location Map - Michigan Avenue Improvement Project (Kenilworth to Central)
- Letter to Residents - Notice 02 - Sewer Televising Second Notice - Michigan (Kenilworth to Central)
- Letter to Residents - Notice 03 - Resident Checklist - Michigan (Kenilworth to Central)
- Letter to Residents - Notice 04 - Construction Start-Lead Notice - Michigan (Kenilworth to Central)
- Letter to Residents - Notice 05 - Resident Checklist #2 - Michigan (Kenilworth to Central)
- Letter to Residents - Notice 06 - Water Shutoff 01 - Michigan (Kenilworth to Central)
- Letter to Residents - Notice 07 - Water Shutoff 02 - Michigan (Kenilworth to Central)
- Letter to Residents - Notice 08 - Water Shutoff 03 - Michigan (Kenilworth to Central)
- Letter to Residents - Notice 09 - Construction Delay - Michigan (Kenilworth to Central)
- Letter to Residents - Notice 10 - Driveway Access - Michigan (Kenilworth to Central)
- Letter to Residents - Notice 11 - Driveway Access Extension - Michigan (Kenilworth to Central)
- Letter to Residents - Notice 12 - Driveway Access - Michigan (Kenilworth to Central)
- Letter to Residents - Notice 13 - Driveway Apron Concrete Changes - Michigan (Kenilworth to Central)
- Letter to Residents - Notice 14 - Driveway Access - Michigan (Kenilworth to Central)
- Letter to Residents - Notice 15 - Temporary Road Closures - Michigan (Kenilworth to Central)
- Letter to Residents - Notice 16 - Parkway Grass - Michigan (Kenilworth to Central)
PROJECT UPDATES
Posted Date | Description |
---|---|
August 6, 2021 | Construction is substantially complete. Punch list work is currently in progress. A change order has been approved to balance quantities to date. |
July 23, 2021 | Punch list work is currently in progress. A change order to balance quantities to date has been submitted for consideration at the July 26, 2021 Village Board meeting. |
June 11, 2021 | Construction is substantially complete. Staff has performed a punch list inspection and is working to coordinate the completion of that punch list work. |
May 28, 2021 | Staff is working to coordinate the completion of the remaining punch list work. |
April 30, 2021 | Staff performed a punch list inspection this week. |
April 23, 2021 | New parkway trees were planted this week. Only punch list work remains. |
April 16, 2021 | Punch list work remains including the planting of trees and dressing up any deficiencies with restoration. |
January 1, 2021 | Construction is substantially complete. Punch list work remains. |
December 11, 2020 | Construction is substantially complete. The contractor is working on punch list items. |
December 4, 2020 | Final asphalt surface paving is complete. Parkway restoration is currently in progress and should be completed by the end of the week. |
November 20, 2020 | A preliminary layer of asphalt, or “binder course”, was placed this week. Final asphalt surface paving is expected to be completed next week. Parkway restoration is also expected to be underway next week. |
November 13, 2020 | Construction of new curbs, sidewalks, and driveway aprons has been completed on the north block and is wrapping up on the south block. A preliminary layer of asphalt, or “binder course”, is expected to be placed on both blocks next week. |
November 6, 2020 | Construction on the curbs, sidewalk and driveway aprons have been constructed on the North block and are wrapping on the South block. Asphalt binder is expected to be placed next week for the first course of the road surface. |
October 30, 2020 | Nicor Gas has lowered gas services that were determined during construction to be in conflict with the pavement. Construction on the curbs, sidewalk and driveway aprons have been constructed on the North Block and will advance to the southern block next week. |
October 9, 2020 | Underground utility work is complete. Nicor Gas is in the process of lowering gas services that were determined during construction to be in conflict with the pavement. |
October 2, 2020 | Underground utility work is complete. Nicor Gas is in the process of lowering gas services that were determined during construction to be in conflict with the pavement. |
September 18, 2020 | Underground utility work is finishing up and the pavement removal is underway. Installation of the new storm sewer main is complete, and work is now in progress on water services, sanitary services, and storm drain stubs. |
September 4, 2020 | Underground utility work is currently underway. Installation of the new storm sewer main is complete, and work is now in progress on water services, sanitary services, and storm drain stubs. |
August 28, 2020 | Underground utility work is currently underway. Installation of the new storm sewer main is complete, and work is now in progress on water services, sanitary services, and storm drain stubs. |
July 17, 2020 | Preliminary construction efforts began this week. Full construction operations are expected to begin next week. |
July 10, 2020 | A construction contract has been executed with United Enterprise, LLC. A pre-construction meeting has been held. Construction is expected to begin the week of July 13, 2020. |
July 3, 2020 | A contract for this project has been awarded to United Enterprise, LLC. Staff is in the process of executing contracts. A pre-construction meeting was held and the contractor is looking to begin work the week of July 6th. |
June 26, 2020 | A contract for this project has been awarded to United Enterprise, LLC. Staff is in the process of executing contracts. A pre-construction meeting has also been scheduled. |
June 12, 2020 | A bid opening for this project was held on May 15, 2020. A contract award recommendation has been submitted for consideration at the June 22, 2020 board meeting. |
May 22, 2020 | A bid opening for this project was held on May 15, 2020. Staff is working to review the bids and check the references of bidders. |
May, 15, 2020 | A bid opening was held Friday, May 15, 2020. The apparent low bidder is United Enterprise, LLC, of Brookfield, IL. Staff is reviewing the submitted bid documents. |
May 8, 2020 | This project is currently out to bid. A bid opening is scheduled for May 15, 2020. |
May 1, 2020 | An addendum has been issued for this project. The bid opening has been moved to May 15, 2020. |
April 1, 2020 | The project is official out to bid. Bidding documents can be found at QuestCDN.com, project #6968271. The bid opening is scheduled for May 1, 2020. |
January 3, 2020 | Design continues. Construction is expected to take place in 2020. |
November 15, 2018 | Design continues. |
April 3, 2018 | Design of the project is ongoing. |
December 19, 2017 | A second notice regarding sewer televising was sent to residents. The first notice was combined with another project. |
October 27, 2017 | Design of the project begins. |
Contact Us
-
Michael Guerra, P.E.
Public Works Director
Email the Engineering Division
Online Contact Form
Staff Directory
Office Address
Public Works Department
11 West Home Avenue
Villa Park, Illinois 60181
Mailing Address
Public Works Department
20 South Ardmore Avenue
Villa Park, Illinois 60181
Ph: 630-834-8505
Fx: 630-834-8509
Emergency: 630-834-7447
Hours
Monday through Friday
7:30 a.m. to 4:00 p.m.