2018 ADA Sidewalk Improvement Project

General Information

   
Project Location(s): 14 intersections (see map)
Project Status: Contract Execution
Bid Opening Date: March 20, 2018, 10:00 a.m.
Start Date: May 17, 2018.
Tentative Completion Date: Fall 2018
Contractor: A Lamp Concrete Contractors, Inc.
Construction Engineer: In-House
Design Engineer: In-House
Awarded Contract Amount: $85,220.00
Funding Sources: Capital Projects Fund
      

Objective


To significantly improve the condition of related sidewalk ramps by removal of the old material and reconstructing them to the latest ADA standards.

Description


This project consists of the reconstruction of sidewalk ramps intersections located along Lincoln Avenue from Terrace Street to Roy Drive, at Ridge Road and Roy Drive, both ends of Hugo Court, Mission Avenue from Pleasant Avenue to Terrace Street. The replacement of deteriorated curb sections, restoration of the parkway, and the adjustment of existing utility structures are also included.

Justification


The Village has determined that the condition of the ramps has deteriorated to the point that ramp reconstruction is needed to bring them up to the most recent standards. This project is to be fully funded funded by the Capital Projects Fund.

Bidding Documents Contracts


Project Documents 
Planholders

Organization Organization Address 
Rai Concrete, Inc. 1827 Blackhawk Dr
West Chicago, IL 60185
Davis Concrete Construction 11244 Manhattan Rd
Monee, IL 60449
Lorusso Cement Contractors 1090 Carolina Dr
West Chicago, IL 60185
Alliance Contractors, Inc. 1166 Lake Ave
Woodstock, IL 60098
Landmark Contractors, Inc. 11916 W. Main St
PO Box #1104
Huntley, IL 60142
A Lamp Concrete Contractors, Inc. 1900 Wright Blvd
Schaumburg, IL 60193
 G&M Cement Construction, Inc. 58 W Commercial Rd
Addison, IL 60101 
Schroder & Schroder, Inc. 7306 Central Park Ave
Skokie, IL 60076

Project Updates


Posted Date
Description 
September 13, 2018 Sod restoration is expected to begin next week.
September 6, 2018 Staff is working to get a schedule to complete the sod restoration.
June 14, 2018 Landscape work has been delayed until Fall due to the forecasted high temperatures. Residents have been notified.
June 7, 2018 Landscape work will be completed when weather permits.
June 1, 2018 All concrete work is complete. Landscape work will be completed when weather permits.
May 24, 2018 The concrete curb has been framed and pouring has begun. The sidewalk is expected to be framed and poured next week.
May 17, 2018 Construction removal has been completed. Installation of the new sidewalk is expected the week of May 21, 2018.
May 10, 2018 Construction is expected to begin next week with concrete removal.
May 3, 2018 A pre-construction meeting was held on May 1, 2018. Construction is expected to start in the next couple of weeks.
April 16, 2018 Staff is working to execute contracts and schedule a pre-construction meeting.
March 22, 2018 An award recommendation will be presented to the Board for consideration at the April 9, 2018 Board Meeting.
March 20, 2018 Project bid submittals were opened on the 19th. The apparent low bidder is A Lamp Concrete Contractors, Inc.
March 2, 2018 Project is out to bid. Bid submittals will be opened at 10:00 A.M. on Tuesday, March 20th.