General Information
Project Location(s): | Various (See Map) |
---|
Project Status: | Completed |
---|
Bid Opening Date: | N/A |
---|
Start Date: | August 24, 2017 |
---|
Completion Date: | September 1, 2017 |
---|
Contractor: | Denler, Inc. 19148 South 104th Avenue Mokena, Illinois 60448 |
---|
Construction Engineer: | In-House |
---|
Design Engineer: | In-House |
---|
Awarded Contract Amount: | $48,960.00 |
---|
Adjusted Final Contract Amount: | $48,960.00 |
---|
Funding Sources: | Street Improvement Fund |
---|
Objective
To slow down the deterioration of the Village's asphalt pavements.
Project Documents
Contract Documents