- Home
- Government
- Departments
- Public Works Department
- Engineering Division
- Construction Projects
- Completed Projects
- Completed Projects 2020
- Second Avenue Combined Sewer Separation Project
Second Avenue Combined Sewer Separation Project (Holly to Division)
GENERAL INFORMATION
Project Location(s): | North Second Avenue, Holly Court to Division Street |
---|---|
Project Status: | Contract Execution |
Bid Opening Date: | July 10, 2018, 10:00 a.m. |
Pre-Bid Meeting (Mandatory): | June 26, 2018, 10:00 a.m. |
Construction Start Date: | September 2018 |
Construction Completion Date: | Fall 2018 |
Contractor: | A Lamp Concrete Contractors, Inc. |
Construction Engineer: | Clark Dietz, Inc. |
Design Engineer: | Christopher B. Burke Engineering, Ltd. |
Awarded Contract Amount: | $692,888.00 |
Adjusted Final Contract Amount: | TBD |
Funding Source(s): | Wastewater Fund (Sewer Separation), CDBG-DR Grant |
OBJECTIVE
To lessen the frequency and severity of flooding and sewer backups by separating existing combined sewers.
DESCRIPTION
This project consists of the separation of the existing combined sewer main on North Second Avenue from Holly Court to Division Street. A grant application is expected to be submitted for Community Development Block Grant Disaster Recovery (CDBG-DR) funding for construction.
JUSTIFICATION
The sewer separation was identified by the CBBEL flood control study.
Bidding Documents
Contract Documents
PLANHOLDERS
Organization | Organization Address |
---|---|
Berger Excavating Contractors, Inc. | 1205 Garland Road Wauconda, IL 60084 |
Martam Construction, Inc. | 1200 Gasket Drive Elgin, IL 60120 |
Archon Construction Co., Inc. | 563 S Route 53 Addison, IL 60101 |
A Lamp Concrete Contractors, Inc. | 1900 Wright Boulevard Schaumburg, IL 60193 |
Cerniglia Co. | 3421 W Lake Street Melrose Park, IL 60160 |
Joel Kennedy Construction | 2830 N Lincoln Avenue Chicago, IL 60657 |
K-Five Construction | 999 Oakmont Plaza Drive Westmont, Il 60559 |
Chicagoland Paving Contractors | 225 Telser Road Lake Zurich, IL 60047 |
Bolder Contractors | 316 Cary Point Drive Cary, IL 60013 |
MQ Construction | 4323 N Central Avenue Chicago, IL 60634 |
PROJECT UPDATES
Posted Date | Description |
---|---|
January 3, 2020 | Only punch list work remains. Staff is working with the contractor to coordinate its completion. |
December 20, 2019 | Only punch list work remains. Staff is working with the contractor to coordinate its completion. |
October 18, 2019 | A final balancing change order was approved on October 14, 2019. Only punch list work remains. Staff is working with the contractor to coordinate its completion. |
October 4, 2019 | Punch list work still remains. Staff is working with the contractor to coordinate its completion. |
June 28, 2019 | Punch list work still remains. Staff is working with the contractor to coordinate its completion. |
June 6, 2019 | The contractor is expected to complete patching of two utility repair trenches in the pavement this week or next week. Only punch list work remains. |
May 23, 2019 | The contractor repaired a sanitary sewer service this week. Only punch list work remains. |
April 18, 2019 | Only punch list work remains. Staff met with the consultant engineer and contractor this week to discuss the water main break the occurred in December 2018. |
January 10, 2019 | Only punch list work remains. Staff met with the consultant engineer and contractor this week to discuss the water main break the occurred in December 2018. |
January 3, 2019 | Only punch list work remains. |
December 6, 2018 | No work due to weather. Only punch list work remains. |
November 15, 2018 | All work is complete. The consultant is working on creating a punch list. |
November 1, 2018 | Sod preparation work is complete. HMA surface and sod installation are expected next week. |
October 25, 2018 | Backfill of the curb and landscape restoration is expected to occur next week. |
October 18, 2018 | Installation of the asphalt binder is complete, installation of asphalt driveways is expected to begin next week. |
October 4, 2018 | Removal of the curb on one side has begun and installation of the curb is expected next week. |
September 27, 2018 | All underground work is complete. Removal of the curb is expected to begin next week. |
September 20, 2018 | The installation of the new storm main is complete. Work on installation of other underground improvements will continue until complete. |
September 13, 2018 | Installation of the storm sewer main has begun and will continue until complete. |
September 6, 2018 | Site preparation and saw-cutting began this week. Installation of the sewer is expected to begin next week. |
July 10, 2018 | Bidding for the project has ended and the as-read results are listed in Bid Tabulation under Bidding Documents. |
June 15, 2018 | The project is out to bid. |
January 22, 2018 | A project coordination meeting was held with Christopher B. Burke Engineering. The design engineer is working on Plans and Specs for the project. |
February 3, 2017 | The grant application to fund construction of the project will be submitted on February 22, 2017. |
January 27, 2017 | A Phase II design engineering agreement has been awarded. |
Contact Us
-
Michael Guerra, P.E.
Public Works Director
Email the Engineering Division
Online Contact Form
Staff Directory
Office Address
Public Works Department
11 West Home Avenue
Villa Park, Illinois 60181
Mailing Address
Public Works Department
20 South Ardmore Avenue
Villa Park, Illinois 60181
Ph: 630-834-8505
Fx: 630-834-8509
Emergency: 630-834-7447
Hours
Monday through Friday
7:30 a.m. to 4:00 p.m.