- Home
- Government
- Departments
- Public Works Department
- Engineering Division
- Construction Projects
- Completed Projects
- Completed Projects 2017
- Biermann Avenue Sewer Separation Project
2017 Biermann Avenue Combined Sewer Separation Project (Holly to Division)
General Information
Project Location(s): | North Biermann Avenue, Holly Court to Division Street |
---|---|
Project Status: | Complete |
Bid Opening Date: | June 20, 2017, 10:00 a.m. |
Pre-Bid Meeting (Mandatory): | June 13, 2017, 10:00 a.m. |
Construction Start Date: | September 7, 2017 |
Construction Completion Date: | November 1, 2017 |
Contractor: | A Lamp Concrete Contractors, Inc. 1900 Wright Boulevard Schaumburg, Illinois 60193 |
Construction Engineer: | Edwin Hancock Engineering Company |
Design Engineer: | Christopher B. Burke Engineering, Ltd. |
Awarded Contract Amount: | $429,436.25 |
Adjusted Final Contract Amount: | $333,866.42 |
Funding Source(s): | Wastewater Fund (Sewer Separation), CDBG-DR Grant |
Objective
To lessen the frequency and severity of flooding and sewer backups by separating the existing combined sewer.
Description
This project consists of the separation of the existing combined sewer main on North Biermann Avenue from Holly Court to Division Street. A grant has been awarded under the Community Development Block Grant Disaster Recovery (CDBG-DR) Program for partial funding of construction. This project was previously combined with the Holly Court Area Improvement Project.
Justification
The combined sewer separation was identified by the 2015 Comprehensive Flood Plan and Storm Sewer System Analysis prepared by Christopher B. Burke Engineering, Ltd. (CBBEL).
Bidding Documents
- Plans (NOT FOR BID) (PDF)
- Specifications (NOT FOR BID) (PDF)
- Advertisement for Bids (PDF)
- Bid Tabulation (PDF)
Contract Documents
- None at this time
Project Documents
Planholders
Organization | Organization Address |
---|---|
A Lamp Concrete | 1900 Wright Schaumburg, IL 60193 |
Cerniglia Co. | 3421 W. Lake Street Melrose Park, IL 60160 |
Archon Construction | 563 S. Route 53 Addison, IL 60101 |
John Neri Construction | 770 W. Factory Road Addison, IL 60101 |
K-Five | 13769 Main Street Lemont, IL 60439 |
Martam Construction, Inc. | 1200 Gasket Drive Elgin, IL 60120 |
J. Congdon Sewer | 170-A Alexandra Way Carol Stream, IL 60188 |
Norvilla, LLC | 2701 S. 13th Avenue Broadview, IL 60155 |
Fox Excavating | 1305 S. River Street Batavia, IL 60510 |
V3 Companies | 7325 Janes Avenue Woodridge, IL 60517 |
Scapin Construction LLC | 395 Whispering Pines Inverness, IL 60010 |
ConstructConnect | 3825 Edwards Road Cincinnati, OH 45209 |
Abitua Sewer, Water & Plumbing, Inc. | 8705 Pyott Road Lake in the Hills, IL 60156 |
Patrick Construction, Inc. | 431 Podlin Unit B Franklin Park, IL 60131 |
Mancini Contractors | 481 Scotland Road Lakemoor, IL 60051 |
Elanar Construction Company | 6620 West Belmont Avenue Chicago, IL 60634 |
Swallow Construction Corporation | 4250 Lacey Road Downers Grove, IL 60515 |
Trine Construction Corporation | 27W364 North Avenue West Chicago, IL 60185 |
Project Updates
Posted Date | Description |
---|---|
December 14, 2017 | Construction is complete. Staff is working to close out the project. |
November 02, 2017 | Sod work is complete and a punch list has been generated. |
October 26, 2017 | All that remains is topsoil and sod. This work will begin when weather permits |
October 19, 2017 | All concrete and asphalt work is complete. All that remains is topsoil and sod. |
October 12, 2017 | Installation of all underground work is complete. The curb has also been installed. All concrete work should be completed early next week with asphalt work scheduled for later in the week. |
October 5, 2017 | Installation of the main line storm sewer is complete and remaining underground work should be completed next week. |
September 29, 2017 | Installation of the storm sewer is about 50% complete and expected to continue for another 1-2 weeks. |
September 22, 2017 | Installation of the storm sewer continues. |
September 15, 2017 | Installation of the storm sewer has begun. |
September 8, 2017 | Construction is expected to begin the week of 09/11/2017. |
August 25, 2017 | A pre-construction meeting was held on 08/22/2017 and construction is expected to begin after Labor Day. |
August 18, 2017 | A contract has been awarded to A Lamp. A pre-construction meeting is scheduled for next week. |
August 11, 2017 | Staff has received approval from the County to send a contract to the Board for consideration at the 08/14/2017 Board Meeting. |
August 4, 2017 | Staff is close to receiving approval from the County to send a contract to the Board for consideration. |
July 7, 2017 | DuPage County must approve the contractor and staff is waiting for this approval. Upon County approval staff will prepare a recommendation to the board. |
June 23, 2017 | A bid opening was held on 06/20/2017. A Lamp was the low bidder. |
June 16, 2017 | A pre-bid meeting was held on 06/13/2017. |
June 9, 2017 | The project was advertised for bid on 06/02/2017 with a bid opening on 06/20/2017. |
May 26, 2017 | Staff reviewed final Phase II Plans and Specs and submitted them to County for approval. |
May 5, 2017 | Staff reviewed Plans and Specs and provided final comments to the consultant. |
April 21, 2017 | Staff is working to review final Phase II Plans and Specs. |
April 7, 2017 | Consultant is working to prepare Phase II Plans and Specs. |
March 31, 2017 | Staff met with the consultant to discuss comments and scheduling. |
March 24, 2017 | Staff provided comments on a preliminary set of Plans and Specs. |
January 20, 2017 | Consultant is working to prepare Phase II Plans and Specs. |
Contact Us
-
Michael Guerra, P.E.
Public Works Director
Email the Engineering Division
Online Contact Form
Staff Directory
Office Address
Public Works Department
11 West Home Avenue
Villa Park, Illinois 60181
Mailing Address
Public Works Department
20 South Ardmore Avenue
Villa Park, Illinois 60181
Ph: 630-834-8505
Fx: 630-834-8509
Emergency: 630-834-7447
Hours
Monday through Friday
7:30 a.m. to 4:00 p.m.