Ridge Road Water Main Improvement Project (Yale to Ardmore)

GENERAL INFORMATION

Project Location(s):West Ridge Road, Yale Avenue to Ardmore Avenue
Project Status:Complete
Bid Opening Date:March 13, 2018, 10:00 a.m.
Construction Start Date:May 28, 2018
Construction Completion Date:Fall 2018
Contractor:Chicagoland Paving Contractors, Inc.
Construction Engineer:Engineering Resource Associates, Inc.
Design Engineer:Baxter & Woodman, Inc.
Awarded Contract Amount:$649,900.00
Adjusted Final Contract Amount:$622,466.18
Funding Source(s):GO Bonds, Water Supply Fund, Wastewater Fund, Community Development Block Grant (CDBG)

OBJECTIVE

To significantly improve the condition of the roadway by removing the existing deteriorated pavement and replacing it with a new structurally sound pavement. To improve water system capacity and reliability by replacing the existing water main.

DESCRIPTION

This project consists of the rehabilitation of Ridge Road from Yale to Ardmore. The project also includes replacement of the existing water main. The water main improvements are budgeted as part of IEPA Water Loan Group #3. Some selective sanitary sewer system improvements are included.

JUSTIFICATION

The Village's pavement management program has determined that the condition of the street has deteriorated to the point that pavement rehabilitation is needed. This project is to be partially funded by voter approved bond proceeds.

PLANHOLDERS

OrganizationOrganization Address
Acqua Construction Corp.1415 S Ardmore Avenue
Villa Park, IL 60181
Chicagoland Paving Contractors225 Telser Road
Lake Zurich, IL 60047
PirTano Construction Company, Inc.1766 Armitage Court
Addison, IL 60101
J. Congdon Sewer Service, Inc.170A Alexandra Way
Carol Stream, IL 60188
Schroeder Asphalt Services, Inc.11022 Grant Highway
Huntley, IL 60142
Trine Construction Corp.27W364 North Avenue
West Chicago, IL 60185
Brothers Asphalt Paving, Inc.315 S Stewart Avenue
Addison, IL 60101
Gerardi Sewer & Water Co.4520 N Osage Avenue
Norridge, IL 60706
Cerniglia Co.3421 W Lake Street
Melrose Park, IL 60160
G&M Cement Construction, Inc.58 W Commercial Road
Addison, IL 60101
Berger Excavating Contractors, Inc.1205 Garland Road
Wauconda, IL 60084
Archon Construction Co., Inc.563 S Route 53
Addison, IL 60101
A Lamp Concrete Contractors, Inc.1900 Wright Boulevard
Schaumburg, IL 60193
K-Five Construction Corperation999 Oakmont Plaza Dr, Suite 200
Westmont, IL 60559
Martam Construction1200 Gasket Dr
Elgin, IL 60120
Norvilla2701 S 13th Avenue
Broadview, IL, 60155

PROJECT UPDATES

Posted DateDescription
December 20, 2019All work is complete. Staff has processed final payment to the contractor. This project is now closed
September 20, 2019A final balancing change order has been approved. Staff is working to close out the project.
August 2, 2019Staff is working to close out the project.
April 18, 2019A final balancing change order has been approved. Staff is working to close out the project.
March 7, 2019Staff is working to close out the project.
January 3, 2019A final balancing change order has been approved. Staff is working to close out the project.
December 13, 2018A final balancing change order has been submitted for consideration at the upcoming December 17, 2018 Village Board meeting. Staff is working to close out the project.
October 18, 2018All work is complete and staff is working to close out the project.
September 20, 2018All that remains is punch list work.
September 6, 2018Sod has been installed. Only Punch List work remains.
August 17, 2018All asphalt work is complete, and the topsoil has been installed. Sod will be installed when weather permits.
August 10, 2018All concrete and underground work is complete. Asphalt work will be completed next week.
August 3, 2018The new water main has passed chlorination testing and installation of services has begun.
July 27, 2018The contractor is still working to pass the chlorination testing.
July 19, 2018The new water main has passed the pressure test and is undergoing the chlorination process.
July 12, 2018Installation of the water main is complete. Upon passing the pressure test and chlorination, installation of the services will begin.
July 5, 2018Installation of the new water main is nearly complete. Once completed, pressure testing and chlorination will begin.
June 28, 2018The installation of the water main continues.
June 21, 2018The contractor has begin installation of the water main this week. Water main work is expected to continue for until completion.
June 1, 2018The contractor is working to receive approval from HUD to begin work.
May 24, 2018Construction is expected to begin next week.
May 21, 2018Construction start notices were delivered to residents.
May 10, 2018Construction is expected to begin the week of May 28, 2018.
May 3, 2018A pre-construction meeting was held on May 3, 2018. Construction cannot begin until school ends for the summer.
April 26, 2018A pre-construction meeting is scheduled for May 3, 2018.
April 19, 2018A Phase III construction engineering agreement will be presented to the Board for consideration at the April 23, 2018 board meeting.
March 29, 2018Staff is working to execute contracts and schedule a pre-construction meeting.
March 15, 2018A bid opening was held on March 13, 2018. Chicagoland Paving was the apparent low bidder. Staff will prepare an award recommendation for the Board to consider at the March 26, 2018 Board Meeting.
March 8, 2018A pre-bid meeting was held on March 6, 2018. The bid opening is scheduled for March 13, 2018.
February 26, 2018Project is out to bid. Bid submittals will be opened at 10:00 A.M. on March 13, 2018.
February 22, 2018The project will be advertised for bidding on February 23, 2018.
February 15, 2018The County has reviewed the draft bid manual and the consultant is working to address the related comments.
February 1, 2018The design engineer is working on plans and specs.
January 18, 2018Staff has reviewed Plans and Specs and have submitted comments to the consultant.
December 14, 2017Grant funds for this project have been released. Staff expects to bid the project in early 2018.
October 12, 2017The County is still waiting for funds to be released for the project. Once funds are released staff will move forward with bidding the project.
October 5, 2017A CDBG Grant kickoff meeting was held on October 4, 2017. The County is still waiting for funds to be released for the project.
June 29, 2017Consultant is working to prepare Phase II Plans and Specs.
June 23, 2017Staff was notified that DuPage County has received the CDBG funds and the project can proceed to bidding when all documents are ready.
April 14, 2017Consultant is working to prepare Phase II Plans and Specs.
April 7, 2017A meeting was held with the consultant on April 5, 2017 to discuss the location of the new water main and other construction concerns.
February 10, 2017Consultant is working to prepare Phase II Plans and Specs.
February 3, 2017A pre-construction meeting was held on February 3, 2017.
January 27, 2017A Phase II design engineering agreement has been awarded.
January 20, 2017A Phase II design engineering agreement will be presented to the board for consideration at the January 23, 2017 Board meeting.
January 6, 2017A proposal to design the improvements was requested from an engineering consultant.
December 2, 2016DuPage County will be recommending that this project be awarded the full amount of CDBG grant funding requested.