- Home
- Government
- Departments
- Public Works Department
- Engineering Division
- Construction Projects
- Completed Projects
- Completed Projects 2017
- Washington Street Green Infrastructure Improvement
Washington Street Green Infrastructure Improvements
GENERAL INFORMATION
Project Location(s): | Grant - Washington to south end Washington - Illinois to Summit Washington - Addison to Wisconsin 546 South Euclid Avenue |
---|---|
Project Status: | Complete |
Bid Opening Date: | August 15, 2017, 10:00 a.m. |
Construction Start Date: | September 14, 2017 |
Construction Completion Date: | November 2017 |
Contractor: | Chicagoland Paving Contractors, Inc. |
Construction Engineer: | TranSystems Corporation |
Design Engineer: | Conservation Design Forum |
Awarded Contract Amount: | $859,999.20 |
Adjusted Final Contract Amount: | TBD |
Funding Source(s): | GO Bonds; CDBG-DR |
Objective
To reduce stormwater runoff to combined sewers, reduce flooding, and increase stormwater quality in the Washington Street combined sewer area, including Grant Avenue.
Description
This project consists of green stormwater infrastructure improvements at four proposed locations: Grant Avenue from Washington Street to the south end; Washington Street between Illinois Avenue and Summit Avenue; Euclid Avenue north of Washington Street; and the vicinity of Washington Street and Addison Avenue. Proposed improvements include permeable pavers (Grant), bio-retention areas, rain gardens, perforated drains, and a naturalized detention area (Euclid).
Justification
The Village expects to receive $1 million in Community Development Block Grant Disaster Recovery (CDBG-DR) funding through Du-Page county for construction of these improvements and an additional $40,000.00 from DuPage County for engineering design.
Bidding Documents
- Advertisement for Bids - Washington Street Green Infrastructure Improvements
- Plans - NOT FOR BID - Washington Street Green Infrastructure Improvements
- Specs - NOT FOR BID - Washington Street Green Infrastructure Improvements
- Addendum #01 - Washington Street Green Infrastructure Improvements
- Bid Tabulation - Washington Street Green Infrastructure Improvements
Contract Documents
- Phase II Engineering - Conservation Design Forum - Washington Street Green Infrastructure Improvements
- Phase III Engineering - TranSystems Corporation - Washington Street Green Infrastructure Improvements
- Construction - Chicagoland Paving Contractors, Inc. - Washington Street Green Infrastructure Improvements
Related Documents
- Intent to Release Funds - DuPage County - Washington Street Green Infrastructure Improvements
- Request for Qualifications - Preliminary - Washington Street Green Infrastructure Improvements
- Letter to Residents - Notice 01 - Public Meeting - Washington Street Green Infrastructure Improvements
- Letter to Residents - Notice 02 - Construction Start - Washington Street Green Infrastructure Improvements
- Letter to Residents - Notice 03 - Driveway Access - Washington Street Green Infrastructure Improvements
- Letter to Residents - Notice 04 - Construction Start - Washington Street Green Infrastructure Improvements
- Letter to Residents - Notice 06 - Construction Resume - Washington Street Green Infrastructure Improvements
PLANHOLDERS
Organization | Organization Address |
---|---|
A Lamp Concrete | 1900 Wright Schaumburg, IL 60193 |
Archon Construction | 563 S. Route 53 Addison, IL 60101 |
John Neri Construction Company Inc. | 770 Factory Road Addison, IL 60101 |
K-Five | 13769 Main Street Lemont, IL 60439 |
Alliance Contractors | 1166 Lake Avenue Woodstock, IL 60098 |
Chicagoland Paving Contractors, Inc. | 225 Telser Road Lake Zurich, IL 60047 |
Elanar Construction | 6620 W. Belmont Avenue Chicago, IL 60634 |
Martam Construction, Inc. | 1200 Gasket Dr. Elgin, IL 60120 |
Landmark Contractors, Inc. | 11916 W. Main Street Road Huntley, IL 60142 |
Norvilla, LLC | 2701 S. 13th Avenue Broadview, IL 60155 |
H. Linden & Sons Sewer & Water | 722 E. South St. Plano, IL 60545 |
Kee Construction LLC | 11002 South Whipple Chicago, IL 60655 |
Gerardi Sewer & Water | 4520 North Osage Norridge, IL 60706 |
J S Excavating Contractors | 16N158 Tyrrell Road Elgin, IL 60124 |
PROJECT UPDATES
Posted Date | Description |
---|---|
June 19, 2020 | This project is now closed out. |
June 12, 2020 | A final balancing change order has been approved. Staff is now working to close out the project. |
April 17, 2020 | Staff is working to close out the project. |
December 20, 2019 | Staff is working to close out the project. |
November 1, 2019 | Staff is working to close out the project. |
July 11, 2019 | The trees that were planted as a part of this project but did not survive have been replaced. Staff is now working to close out the project. |
July 3, 2019 | The trees that were planted as a part of the project but did not survive were replaced this week. |
June 28, 2019 | Replacement trees have been ordered by the contractor and are expected to be installed upon receipt. |
May 23, 2019 | Some of the trees that were planted as planted of the project have not survived and must be replaced. Staff is working to coordinate the tree replacement. |
March 28, 2019 | Staff is working to close out the project. |
January 3, 2019 | Staff is working to close out the project. |
November 1, 2018 | All work is complete and Staff is working to close out the project. |
October 25, 2018 | All corrective work at 546 S Euclid is complete. Staff will monitor the side to ensure it functions as intended. |
October 18, 2018 | Corrective work has begun at 546 S Euclid and is expected to be completed next week. |
July 5, 2018 | A possible solution to the drainage issue at 546 S Euclid has been determined and staff is awaiting probable construction costs. A change order may be necessary to implement the improvements. |
June 28, 2018 | Staff, the consultant, and the contractor are working together to determine why the basin at 546 S Euclid does not drain properly. |
June 7, 2018 | The restoration of parkways and plantings is complete. |
May 10, 2018 | All excavation work is complete. Restoration of parkways and plantings will begin when weather permits. |
May 3, 2018 | All underground work is complete. Concrete work has begun and is expected to be completed within next week. |
April 26, 2018 | Underground work on west Washington at Addison is nearly complete. A construction contractor hit an incorrectly marked gas main while installing the new sewer, resulting in a significant fire and police presence. |
April 19, 2018 | Excavation of the west Washington area has been completed and excavation of the property formerly at 546 S Euclid has begun. Installation of storm structures is expected to begin next week. |
April 12, 2018 | Construction has resumed, with excavation of the parkways on the W Washington section of the project. |
April 5, 2018 | Due to weather, construction was unable to start the week of April 2. Construction is expected to begin the week of April 9. |
March 29, 2018 | A meeting to discuss the construction startup was held on March 28, 2018. A letter providing information about the resumption of construction on unfinished areas of the Project was delivered to residents. Construction is expected to begin the week of April 2 2018. An electronic copy can be found in the Project Documents section. |
March 22, 2018 | A meeting to discuss construction startup is scheduled for March 28, 2018. |
January 11, 2018 | DuPage County Health Department has given approval to demolish the house at 546 S Euclid Avenue A demolition schedule is expected soon. Detailed information on this project can be found here. |
December 21, 2017 | Work will resume when weather permits. |
November 16, 2017 | The Installation of pavers on Grant is complete and Grant has been reopened to traffic. The contractor is preparing to place topsoil in the bioswales on East Washington Street. Bid opening for demolition of 546 South Euclid was held on 2017. The apparent low bidder is Alpine Demolition Services of St. Charles, Illinois, with a bid of $27,000.00. The bid is currently under review by DuPage County. |
November 9, 2017 | The majority of the pavers on Grant have been installed. The remaining pavers are those required to be cut to smaller sizes. |
November 2, 2017 | Concrete on Grant is complete. Additional stone and pavers should be installed over the next couple weeks. Excavation of the remaining portion of E. Washington is complete. Nicor is working to relocate the main on W. Washington. |
October 26, 2017 | Installation of concrete has begun. All concrete on Grant is expected to be completed next week. Nicor should complete work on E. Washington this week and the contractor will begin their work next week. |
October 19, 2017 | Installation of the aggregate for the permeable pavers street and bioswales on Grant has begun. Nicor has started the relocation of their utility and is expected to continue until complete. |
October 5, 2017 | Underground work has begun and is expected to continue for the next couple weeks. A permit has been issued to Nicor to relocate their utility, which is in conflict with the proposed improvements, and Staff is attempting to get a schedule from Nicor in an effort to not delay the project. |
September 29, 2017 | Excavation on Grant is nearly complete. Installation of the underdrain system will be starting shortly. The intersection of Washington and Summit will likely be closed for 1 day as part of construction. |
September 22, 2017 | Bioswale on the east side of Grant is dug and rough graded as well as the section on the north side of East Washington. The installation of underground work is scheduled to begin next week. |
September 15, 2017 | Tree removal is complete and excavation is expected to begin next week. |
September 8, 2017 | A pre-construction meeting was held on September 7, 2017. Construction is expected to begin in the next couple weeks. |
September 1, 2017 | A contract was awarded at the August 28, 2017 Boar Meeting. Staff is working to schedule a pre-construction meeting. |
August 25, 2017 | Staff is submitting a contract to the Board for consideration at the 08/28/2017 Board Meeting. |
August 18, 2017 | A bid opening was held on August 15, 2017. Staff is in the process of reviewing bids and checking contractor references. A Phase III construction engineering contract has been awarded to Transystems. |
July 28, 2017 | The project was advertised for bid on July 28, 2017. A bid opening is scheduled for August 15, 2017. |
July 21, 2017 | Staff completed final review of the Plans and Specs and submitted them to the County for their approval. |
July 14, 2017 | Staff is working with the design consultant to try and complete the plan in time to put the project out to bid later this month. |
July 7, 2017 | Village staff is working with the consultant to finalize plans and establish a bidding schedule. Public Works staff met with several residents to discuss fence and tree removal. |
June 30, 2017 | A public information meeting was held on June 27, 2017. Village staff has completed review of the updated design report. Final design of this project is not budged in FY 17/18, but this project will be included in the facility plan so it is eligible for low interest IEPA loans in the future. Exhibits of this project were on display at the public information meeting for the Washington Green Infrastructure Project. |
June 16, 2017 | A public information meeting is scheduled for June 27, 2017 at 5:00 p.m. in the Village Board room. Staff submitted comments to the design consultant. |
June 9, 2017 | Staff received revised Phase II Plans and Specs and is working to review them. |
May 12, 2017 | Staff held a conference call with the design engineer to clarify several design elements for the projects. Some revisions to the plans may be needed. We expect pre-final plans to be ready in June 2017. Staff has selected Transystems for Phase III construction engineering and will present a contract to the Board for consideration upon completion of Phase II. The contract approving the purchase of the property at 546 South Euclid has been approved by the Village Board. Closing is expected in June 2017. |
May 5, 2017 | Staff received revise Phase II Plans and Specs and is working to review them. |
April 28, 2017 | The contract approving the purchase of the property at 546 South Euclid has been prepared and will be submitted to the Village Board for consideration in May. Staff has completed interviews of engineering consulting firms for the Phase III construction engineering. Staff is completing its reviewing of the pre-final Plans and Specs. |
March 10, 2017 | Staff received revised Plans and Specs and is working to review them. Staff is reviewing the qualifications submitted by consultants for the Phase III construction engineering services. The public information meetings for Grant Street and Washington Green Infrastructure will be scheduled once the Village receives pre-final plans from the consultant. |
February 24, 2017 | Engineering consultant continues to work on Phase II Plans and Specs. |
February 17, 2017 | County staff will need to review bid documents prior to advertising for bid, which is expected in March. Public information meetings will also be scheduled. Engineering consultant continues to work on Phase II plans and specs. Staff has requested a preliminary qualifications for Phase III construction engineering be submitted by March 3, 2017. |
February 3, 2017 | Due to the CDBG-DR grant funding, a "Project Setup Meeting" with DuPage County staff will be necessary and has been scheduled for February 10, 2017. |
January 27, 2017 | Engineering staff met with Conservation Design Forum (CDF), the Phase II design engineer, to discuss staff review comments and the timetable for public information meeting and bidding the project. CDF does not provide Phase III construction engineering services, so another engineering firm will need to be selected. CDF will provide plan clarifications during construction on an as-needed basis. |
January 6, 2017 | Village staff will be presenting a CDBG-DR funding agreement that would provide $1,000,000 for the Washington Green Infrastructure Project to the Village Board on 01/07/2017. This project includes permeable pavers on Grant Street as well as bioswales along Washington Street. |
December 9, 2016 | Village staff has received the CDBG-DR funding agreement that would provide $1,000,000 for the Washington Green Infrastructure Project. Additional funding for the purchase and demolition of the property has also been approved by the County Community Development Commission. An amendment to the previous funding agreement will be required. |
November 18, 2016 | The consultant has submitted a tentative construction schedule with a tentative March 2017 letting date. A funding agreement with DuPage County needs to be executed prior to bidding. |
September 30, 2016 | Staff has completed its review of the 50% plans and submitted comments to the consultant. |
September 23, 2016 | A purchase order for the property appraisal has been submitted. Grant documents have been forwarded to DuPage County for execution. |
September 16, 2016 | The Village Board approved a proposed inter-governmental agreement to provide CDBG-DR funding towards the purchase and demolition of a house on South Euclid. The next step will be to obtain property appraisals. |
September 2, 2016 | Staff held a progress meeting with the consultant to review 50% plans and to compare with preliminary plans for the Washington Combined Sewer Separation study. |
June 3, 2016 | Staff is investigating options for additional off-site storage near Grant Street. |
May 27, 2016 | Staff walked the project limits with the consultant. Diseased and end of life trees will need to be identified for potential removal. |
May 6, 2016 | Additional survey work has been completed and submitted to Conservation Design Forum (CDF), consultant for design of the Washington Corridor Green Infrastructure Project. Coordination with the Burke study, grant eligibility of work items ($1 million CDBG-DR), and scope of work are key factors. |
April 29, 2016 | Additional survey work has been scheduled. |
April 1, 2016 | A kick-off meeting was held with CDF on March 28, 2016. Design of the proposed green infrastructure improvements has begun. |
March 18, 2016 | Kick-off meeting with Conservation Design Forum (CDF) for design of the Washington Corridor Green Infrastructure Improvements to be scheduled in the near future. County has issued public notice to release the $1 million grant funds for the this project. |
March 11, 2016 | A design contract has been submitted to the Board for consideration at the March 14, 2016 Board Meeting. |
February 26, 2016 | Village staff reviewing a proposal from Conservation Design Forum (CDF) for design of the Washington Corridor Green Infrastructure Improvements. |
February 19, 2016 |
|
Contact Us
-
Michael Guerra, P.E.
Public Works Director
Email the Public Works Department
Office Address
Public Works Department
11 West Home Avenue
Villa Park, Illinois 60181
Mailing Address
Public Works Department
20 South Ardmore Avenue
Villa Park, Illinois 60181
Ph: 630-834-8505
Fx: 630-834-8509
Hours
Monday through Friday
7:30 a.m. to 4:00 p.m.