- Home
- Government
- Departments
- Public Works Department
- Engineering Division
- Construction Projects
- Completed Projects
- Completed Projects 2015
- 2015 Concrete Street Improvement Program
2015 Concrete Street Improvement Program
General Information
Project Location(s): | N/A |
---|---|
Project Status: | Construction Complete |
Start Date: | N/A |
Tentative Completion Date: | N/A |
Contractor: | G&M Cement Construction, Inc. |
Construction Engineer: | Clark Dietz, Inc. |
Design Engineer: | Robinson Engineering |
Awarded Contract Amount: | N/A |
Funding Sources: | Street Improvement; GO Bonds |
Description
This project consists of improvements on various streets in the Village of Villa Park. The total length of the improvements is approximately 5,600 lineal feet. The scope of work includes Portland cement concrete (PCC) pavement, Portland cement concrete (PCC) pavement patching, Portland cement concrete (PCC) surface diamond grinding, combination concrete curb and gutter removal and replacement, structure adjustments, pavement markings, and other related and incidental work efforts.
Map
Bidding Documents
Bid Tabulation
Contracts
- Contract (PDF)
- Street Improvements 2015 - Phase II Engineering Agreement (PDF)
- Street Improvements 2015 - Phase III Engineering Agreement (PDF)
Project Related Documents
Planholders
Organization | Organization Address |
---|---|
J Nardulli Concrete, Inc. | 3517 South 60th Court Cicero, IL 60804 |
R.W. Dunteman Co. | P.O. Box 1129 600 South Lombard Road Addison, IL 60101 |
G&M Cement Construction Inc. | 58 West Commercial Road Addison, IL 60101 |
A. Lamp Concrete Contractors, Inc. | 1900 Wright Boulevard Schaumburg, IL 60193 |
Triggi Construction | 1975 Powis Road West Chicago, IL |
MQ Construction Company | 4323 North Central Avenue Chicago, IL 60634 |
Schroeder and Schroeder, Inc. | 7306 Central Park Skokie, IL 60076 |
Martam Construction Co. | 1200 Gasket Drive Elgin, IL 60120 |
Orange Crush, LLC. | 321 Center Street Hillside, IL 60162 |
JG Demo, Inc. | 134 W. Lake Street Addison, IL 60101 |
Landmark Contractors | 11916 West Main Street PO Box 1104 Huntley, IL 60142 |
Alliance Contractors, Inc. | 1166 Lake Avenue Woodstock, IL 60098 |
Project Updates
Posted Date | Description |
---|---|
March 4, 2016 | Project is closed out. |
February 5, 2016 | Staff continues to close out 2015 projects, including preparation of final change orders and processing final pay requests. |
January 15, 2016 | A final balancing change order was approved at the 01/11/2016 board meeting. Staff has submitted a final pay request. |
January 8, 2016 | A final balancing change order has been submitted for the 01/11/2016 board meeting. |
November 13, 2015 | The only work which remains at this point is the placement of pavement markings and the completion of punch list work. |
October 30, 2015 | Construction of this project is substantially complete. Most restoration work, including landscaping and patching of driveways is complete. The only work which remains at this point is the sealing of joints in the concrete pavement and the completion of punch list work. |
October 23, 2015 | Diamond grinding of Adele, Armitage, Ellsworth and Sidney was completed this week. Restoration work began this week with patching and paving of asphalt driveways. Landscaping restoration work must still take place. |
October 16, 2015 | Pavement patching on Adele, Armitage, Ellsworth and Sidney is complete. Diamond grinding of those streets began this week and is expected to continue into next week. Paving of the north half of Stone Road is mostly complete. A few remaining gaps which were needed to maintain access to the businesses were poured this week. Some remaining concrete and restoration work must still take place. |
October 9, 2015 | Remaining patching on Ellsworth continued this week. That patching work should be completed next week. Paving of the north half of Stone Road began this week. That work should also be complete within the next one to two weeks. |
October 2, 2015 | Patching of the east half of Ellsworth began this week. That patching work should be completed next week. Preparation for paving of the north half of Stone Road continued this week. That work should also be completed next week. |
September 25, 2015 | Paving of the intersections in the south half of Stone Road took place this week. The south half of Stone Road is now complete. Patching of the west half of Ellsworth was mostly completed this week. Work on the north half of Stone Road and the east half of Ellsworth is expected to begin next week. |
September 18, 2015 | Paving of the south half of Stone Road was completed this week. Patching of Armitage, Sidney and Adele was also completed this week. Paving of the intersections on Stone Road and patching of Ellsworth are expected to begin next week. |
September 11, 2015 | Paving of Stone Road began this week, but was halted by weather. Paving should continue early next week. Sawcutting for patches on Ellsworth is currently in progress. Patches on the first side of the street on Adele, Armitage, and Sidney are complete. |
September 4, 2015 | Sawcutting on Stone and Ellsworth is currently in progress. Patch and curb removal and pouring on Adele, Armitage, and Sidney for the first side of the street is in progress. Pavement removal on Stone has begun. |
August 28, 2015 | Sawcutting for concrete pavement patching has been completed on Adele, Armitage and Sidney, and is expected to begin next week on Ellsworth. Removal of pavement for patching may begin next week, depending on the progress of sawcutting. Sawcutting of the curb line on Stone Road began this week and is expected to be completed early next week. |
August 21, 2015 | Sawcutting for concrete pavement patching continued this week and is expected to continue through most of next week. Removal of pavement for patching may begin next week, depending on the progress of sawcutting. |
July 24, 2015 | Staff held a pre-construction meeting for this project this week. Construction is tentatively expected to begin in mid-August. |
July 17, 2015 | Contracts for the two asphalt projects and the concrete projects have been awarded and contract documents submitted to the successful bidders for execution. Clark-Dietz will be providing Phase III resident inspection with assistance from Village staff. Pre-construction meetings will be scheduled as soon as contracts are executed. |
July 10, 2015 | Bids were opened for this project. Contract award recommendations will be submitted to the Village Board for the July 13, 2015 meeting. |
June 26, 2015 | Village staff will be presenting a contract to provide Phase III engineering to the Village Board for consideration. |
June 19, 2015 | The concrete related contract for the 2015 Street Improvement Program were advertised on June 19, 2015. Village staff is completing negotiation for a separate contract to provide Phase III engineering to be presented to the Village Board for consideration. |
May 29, 2015 | Staff will be reviewing plans, specifications, and cost estimates as they are completed by the consultant. There are a few minor drainage issues that still need to be resolved. |
May 22, 2015 | A tentative bid date of 05/29/2015 has been established for the 2015 Street Improvement Program. Two contracts will be let, one for concrete pavements and one for asphalt pavements. We would expect work to commence late July or early August. |
April 3, 2015 | Design for the 2015 road improvements (Robinson Engineering) continues. All streets have been driven and the geotechnical information provided to the consultant. Staff expects to receive pre-final cost estimates with the next few days. |
Contact Us
-
Michael Guerra, P.E.
Public Works Director
Email the Engineering Division
Online Contact Form
Staff Directory
Office Address
Public Works Department
11 West Home Avenue
Villa Park, Illinois 60181
Mailing Address
Public Works Department
20 South Ardmore Avenue
Villa Park, Illinois 60181
Ph: 630-834-8505
Fx: 630-834-8509
Emergency: 630-834-7447
Hours
Monday through Friday
7:30 a.m. to 4:00 p.m.