To improve the condition of the roadway by milling the existing, deteriorated pavement surface and replacing it with a new pavement surface in select areas.
Posted Date | Description |
---|---|
July 3, 2015 | Construction is complete and final payment has been made. |
May 8, 2015 | Staff is in the process of marking out patches. Work is tentatively scheduled to start the week of 05/25/2015. |