- Home
- Government
- Departments
- Public Works Department
- Engineering Division
- Construction Projects
- Completed Projects
- Completed Projects 2020
- Astor, Myrtle, and Euclid Improvement Project
Astor, Myrtle, and Euclid Improvement Project
GENERAL INFORMATION
Project Location(s): | Astor Court - Summit to Myrtle Myrtle Avenue - Park to Highland Euclid Avenue - Kenilworth to Highland |
---|---|
Project Status: | Closeout |
Bid Opening Date: | September 10, 2019 |
QuestCDN Project Number: | 6455887 |
Construction Start Date: | Spring 2020 |
Construction Completion Date: | 2020 |
Contractor: | A Lamp Concrete Contractors, Inc. |
Construction Engineer: | TranSystems Corporation |
Design Engineer: | RJN Group, Inc. |
Awarded Contract Amount: | $2,434,983.80 |
Adjusted Final Contract Amount: | TBD |
Funding Source(s): | GO Bonds; Flood Control; Sewer Separation; Water Supply; Wastewater |
OBJECTIVE
To significantly improve the condition of the roadway by removing the existing deteriorated pavement and replacing it with a new structurally sound pavement. A portion of the project includes storm sewer that will reduce the frequency of surcharging of the combined sewer system.
DESCRIPTION
This project consists of the reconstruction of Astor Court from Summit Avenue to Myrtle Avenue, Myrtle Avenue from Park to Highland, and Euclid Avenue from Kenilworth to Highland, and includes storm sewer construction. Some selective water system and sanitary sewer system improvements are also included.
JUSTIFICATION
The Village's pavement management program has determined that the condition of the street has deteriorated to the point that pavement rehabilitation is needed. This project is to be partially funded by voter approved bond proceeds.
The sanitary sewer separation and related work for the Astor, Myrtle, and Euclid Improvement Project were financed by the Water Pollution Control Loan Program (WPCLP) State Revolving Fund (SRF). The SRF program is administered by the Illinois Environmental Protection Agency and receives a portion of its money to fund these types of projects from the U.S. Environmental Protection Agency. This project includes areas throughout the Village of Villa Park. Once complete, it will improve water quality for area residents and businesses in Villa Park and the Salt Creek Watershed by reducing the inflow and infiltration (I/I) of both stormwater and debris into the sanitary sewer system, thus lessening both the frequency and severity of sewer surcharges and sewer backup. SRF programs operate in each state to provide communities the resources necessary to build, maintain, and improve the infrastructure that protects one of our most valuable resources: water.
Bidding Documents
Contract Documents
- Facility Plan - RJN Group, Inc. - Astor, Myrtle, and Euclid Improvement Project
- Amendment to Engineering Services - Phase II Engineering - RJN Group, Inc. - Euclid
- Phase III Engineering - TranSystems Corporation - Astor, Myrtle, and Euclid
- Construction - A Lamp Concrete Contractors, Inc. - Astor Myrtle and Euclid Improvement Project
Related Documents
- Location Map - Astor, Myrtle, and Euclid Improvement Project
- Letter to Residents - Notice 01 - Resident Checklist - Astor, Myrtle, and Euclid
- Letter to Residents - Notice 05 - Sewer Service Televising - Euclid
- Letter to Residents - Notice 06 - Sewer Service Televising Second Notice - Astor and Myrtle
- Letter to Residents - Notice 07 - Resident Checklist Second Notice - Astor, Myrtle, and Euclid
- Letter to Residents - Notice 08 - Construction Start - Astor, Myrtle, and Euclid
- Letter to Residents - Notice 09 (Water Shutoff 01) - Astor, Myrtle, and Euclid
- Letter to Residents - Notice 10 (Water Shutoff 02) - Astor, Myrtle, and Euclid
- Letter to Residents - Notice 11 (Water Shutoff 03) - Astor, Myrtle, and Euclid
- Letter to Residents - Notice 12 (Water Shutoff 04) - Astor, Myrtle, and Euclid
- Letter to Residents - Notice 13 (Water Shutoff 05) - Astor, Myrtle, and Euclid
- Letter to Residents - Notice 14 ( Driveway Access at Vault) - Astor, Myrtle, and Euclid
PLANHOLDERS
Organization Name | Organization Address |
---|---|
See project webpage at QuestCDN |
PROJECT UPDATES
Posted Date | Description |
---|---|
January 14, 2022 | A final, balancing change order is expected to be submitted for consideration at the January 24, 2022 Village Board meeting. |
December 4, 2020 | Staff is working on closing out the project. |
November 13, 2020 | Construction is complete. Staff is working on closing out the project. |
November 6, 2020 | The project is substantially complete. Punch list work is being completed and the project is expected to be completed by the end of next week. |
October 23, 2020 | The project is substantially complete. Punch list work is pending and is expected to be completed in the next two weeks. |
October 2, 2020 | The project is substantially complete. Staff is in the process of preparing a punch list for the contractor to address. |
September 18, 2020 | Paving of the final surface layer of asphalt is expected to be completed by Friday with landscaping and punch list items to follow next week. |
September 11, 2020 | Paving of a preliminary layer of asphalt, or “binder course” is complete. The backfilling of the parkway is completed. Paving of the final surface layer of asphalt is expected to be completed early next week due to delays with weather. |
September 4, 2020 | The backfilling of the parkway is completed. Paving of the final surface layer of asphalt is expected to be completed at the end of next week. |
August 28, 2020 | Paving of a preliminary layer of asphalt, or “binder course” was completed this week. Paving of the final surface layer of asphalt is expected to be completed in the next one to two weeks. |
July 24, 2020 | Construction is underway. The concrete slab foundation for the new StormTrap underground stormwater detention vault was constructed this week. The concrete slab will need to cure, and the installation of the new pre-cast vault sections will follow. |
July 17, 2020 | Construction is underway. Excavation for the underground stormwater detention vault is nearing completion. Construction of the concrete slab foundation for the vault is expected to begin next week. |
July 10, 2020 | Construction is underway. Installation of underground utilities is nearing completion. Excavation for the underground stormwater detention vault started this week. |
July 3, 2020 | Installation of underground utilities is nearing completion. Work on removal of existing pavement is underway with the installation of the underground storage tank starting next week. Public Works has requested to the Police not to enforce the overnight parking restriction in this area starting next week as residents will have limited access to their properties with paving operations. |
May 22, 2020 | Construction is underway. Installation of the new storm sewer is currently in progress. Some water system improvements have also been completed. |
May 8, 2020 | Construction is underway. Installation of the new storm sewer is currently in progress. |
May 1, 2020 | Construction started this week. Installation of the new storm sewer is currently in progress. |
April 24, 2020 | Construction is expected to start on April 27, 2020. Staff is coordinating those efforts. |
April 17, 2020 | IEPA loan approval was received this week. Staff is coordinating the start of construction, tentatively expected for the week of April 27, 2020. |
April 3, 2020 | The IEPA has indicated that loan approval should be received within the next week. Staff has held a pre-construction meeting and is coordinating the start of construction, pending receipt of the loan approval. |
March 27, 2020 | Staff has held a pre-construction meeting. The IEPA has indicated that loan approval should be received in the next few weeks. |
March 20, 2020 | Staff held a pre-construction meeting this week. The IEPA has indicated that loan approval should be received in the next few weeks. |
March 13, 2020 | Staff is working to obtain IEPA loan approval. The IEPA has indicated that loan approval should be received in the next few weeks. |
March 6, 2020 | Staff is working to obtain IEPA loan approval. The IEPA has indicated that loan approval should be forthcoming. |
February 28, 2020 | Staff is working to obtain IEPA loan approval. The IEPA has been requesting additional documentation and staff has been providing it. |
January 31, 2020 | Staff is working to obtain IEPA loan approval. The IEPA has been requesting additional documentation and staff has been providing it. |
January 3, 2020 | Staff is working to obtain IEPA loan approval. Construction contract award is also pending IEPA review and approval. |
November 8, 2019 | A bid opening for this project was held on September 10, 2019. A conditional construction contract award with A Lamp Concrete Contractors has been approved. The construction contract award is now pending review and approval by the Illinois EPA. A construction engineering services agreement with TranSystems Corporation had already been approved. |
October 18, 2019 | A conditional construction contract award with A Lamp Concrete Contractors has been approved. |
October 11, 2019 | A conditional construction contract award with A Lamp Concrete Contractors has been approved. The construction contract award is now pending review and approval by the Illinois EPA. |
September 13, 2019 | A bid opening for this project was held on September 10, 2019. The apparent low bid was submitted by A Lamp Concrete Contractors. Staff has submitted a recommendation for board consideration to award a contract to A Lamp. A construction engineering services agreement with TranSystems Corporation has already been approved. |
August 30, 2019 | A construction engineering services agreement with TranSystems Corporation has been approved. |
August 22, 2019 | Staff held a pre-bid meeting this week. |
August 15, 2019 | The project was advertised for bidding. Staff expects to submit a proposed construction engineering services agreement with TranSystems Corporation for Village Board consideration. |
July 26, 2019 | This project was advertised for bidding this week. A bid opening is scheduled for September 10, 2019. Bidding documents are available at www.questcdn.com. |
July 3, 2019 | Staff held a progress meeting with the design engineer this week. The design engineer is working to finalize plans and bidding documents. The project should be going out to bid by the end of July. |
April 25, 2019 | The Illinois EPA issued financial approval of the Village’s application for loan funding this week. Staff is now working with the consultant to bid the project. |
March 21, 2019 | The Illinois EPA has issued planning approval and legal approval for this project. The only remaining effort is now financial approval. Staff is now working with the consultant and the IEPA to complete this final step. |
February 7, 2019 | The Illinois EPA has issued planning approval for this project. Staff is now working with the consultant and the IEPA to move this project forward to bidding. |
January 31, 2019 | The Illinois EPA has notified the Village that this project has received planning approval. Staff is now working with the consultant and the IEPA to move this project forward to bidding. |
January 10, 2019 | The Village received a Notice of Intent to Issue a Categorical Exclusion from the Illinois EPA. A public comment period has now passed and staff is working to submit the necessary follow-up documentation to the IEPA. |
January 3, 2019 | The public comment period is now underway. |
December 20, 2018 | The Village received a Notice of Intent to Issue a Categorical Exclusion from the Illinois EPA. A public notice and comment period are now required and are expected to begin next week. |
December 13, 2018 | The Village is awaiting a Notice of Intent to Issue a Categorical Exclusion from the Illinois EPA. |
September 20, 2018 | Staff is awaiting the IEPA response for the loan application, project plan, and approved loan ordinance. |
June 28, 2018 | Staff is awaiting a response on the IEPA loan application and project plan. The loan ordinance has been approved and is now awaiting publication and the public comment period. |
March 22, 2018 | The IEPA loan application and project plan have been submitted to the IEPA, and Staff is awaiting a response. |
December 28, 2017 | The design engineer is working on plans and specifications. |
December 21, 2017 | A design kick-off meeting was held for Euclid, Highland to Kenilworth. |
November 22, 2017 | A proposed amendment to the Phase II design engineering agreement with RJN Group is expected to be submitted for consideration at the Board Meeting on December 4, 2017. The amendment would add the design of South Euclid Avenue from Kenilworth to Central and Park to Highland to this project. |
November 9, 2017 | A resolution related to the IEPA loan for the Astor/Myrtle combined sewer separation will be presented to the Village Board on November 13, 2017. |
July 7, 2017 | Consultant is working to prepare Phase II Plans and Specifications including IEPA loan documents. |
June 30, 2017 | A meeting was held to discuss the Facility Plan for the IEPA loans associated with this project. |
December 30, 2016 | Consultant is working to prepare Phase II Plans and Specifications. |
December 23, 2016 | Staff met with RJN on December 16, 2016 to discuss the remaining design issues. |
December 16, 2016 | Consultant is working to complete Phase II design. |
December 9, 2016 | Review comments were provided to the consultant. |
October 7, 2016 | The consultant has submitted 75% plans for the Village to review. |
August 26, 2016 | Design of the roadway continues as less expensive detention options are being evaluated. |
August 19, 2016 | A progress meeting to discuss the status design was held on August 16, 2016. It was requested that less expensive detention options be evaluated. |
August 12, 2016 | A meeting to discuss the continued design of the project is scheduled for August 16, 2016. |
July 29, 2016 | Engineering consultant RJN submitted options for underground flood storage. |
July 8 ,2016 | Engineering consultant is continuing to work on Phase II design engineering. |
July 1, 2016 | Topographic survey work has been completed. |
June 24, 2016 | Staff is working with the consultant on various tasks related to design. |
June 10, 2016 | A kick-off meeting was held on June 3, 2016. |
May 27, 2016 | A contract with RJN Group was approved at the May 23, 2016 Board meeting. A kick-off meeting is scheduled for June 3, 2016. |
February 12, 2016 | Staff is reviewing the Phase II design engineering proposal from RJN Group. |
January 15, 2015 | Staff received qualifications and has requested a proposal from RJN Group for Phase II Design. |
December 25, 2015 | Staff has requested qualifications for the Phase II Design Engineering of this project. |
October 2, 2015 | Staff has completed its review of a preliminary storm sewer design from engineering consultant RJN Group. Staff is now working with the consultant to address review comments. |
March 13, 2015 | Staff received preliminary storm sewer design from engineering consultant RJN Group this week. Staff is currently working to review the submittal. |
Contact Us
-
Michael Guerra, P.E.
Public Works Director
Email the Engineering Division
Online Contact Form
Staff Directory
Office Address
Public Works Department
11 West Home Avenue
Villa Park, Illinois 60181
Mailing Address
Public Works Department
20 South Ardmore Avenue
Villa Park, Illinois 60181
Ph: 630-834-8505
Fx: 630-834-8509
Emergency: 630-834-7447
Hours
Monday through Friday
7:30 a.m. to 4:00 p.m.