- Home
- Government
- Departments
- Public Works Department
- Engineering Division
- Construction Projects
- Completed Projects
- Completed Projects 2017
- South Summit Avenue Resurfacing Project
2017 South Summit Avenue Resurfacing Project (Madison to Roosevelt)
General Information
Project Location(s): | South Summit Avenue, Madison Street to Roosevelt Road |
---|---|
Project Status: | Construction Complete |
Construction Start Date: | April 2017 |
Construction Completion Date: | July 2017 |
Contractor: | K-Five Construction Corporation |
Construction Engineer: | Robinson Engineering, Ltd. |
Design Engineer: | Clark Dietz, Inc. |
Awarded Contract Amount: | $483,780.58 |
Adjusted Final Contract Amount: | To Be Determined |
Funding Source(s): | Street Improvement Fund; Surface Transportation Program (STP) Grant |
Objective
To improve the condition of the roadway by milling the existing, deteriorated pavement surface and replacing it with a new pavement surface.
Description
This project consists of the resurfacing of the portions of South Summit Avenue from Madison to Roosevelt located in the Village of Villa Park.
Justification
The Village's pavement management program has determined that the condition of this street has deteriorated to the point that pavement rehabilitation is needed. The Federal Surface Transportation Program (STP) is expected to provide funding for a portion of construction costs.
Contract Documents
- Phase II Engineering Agreement - Clark Dietz (PDF)
- Phase III Engineering Agreement - Robinson Engineering (PDF)
Project Documents
- Plans (PDF)
- Specifications (PDF)
- Letter - Residents - Notice 01 (Construction Start) - Summit S Resurfacing 2017 (PDF)
Project Updates
Posted Date | Description |
---|---|
June 23, 2017 | A punch list was created of items including poor restoration work and provided to the contractor. |
June 9, 2017 | Restoration of the parkway is complete. A punch list needs to be created to finish the job. |
May 26, 2017 | Restoration of the parkway is nearly complete. Upon its completion a punch list will be created to finish the job. |
May 12, 2017 | Surface paving has begun and may be completed this week, weather permitting. |
May 5, 2017 | The level binder was installed and surface is scheduled for next week. |
April 28, 2017 | The plan is to have the HMA level binder installed next week with structure adjustments to follow. |
April 21, 2017 | The asphalt surface has been removed and the contractor is working on asphalt base patches. The asphalt level binder will be installed when IDOT approves the test strip and all patching is complete. |
April 14, 2017 | Concrete work is expected to be completed in the next week. Shortly after completion of the concrete work asphalt pavement grinding will begin. |
April 7, 2017 | Construction began this week. Concrete work is currently underway. |
March 31, 2017 | Construction is expected to begin the week of 04/03/2017. |
March 24, 2017 | A pre-construction meeting was held with IDOT on 03/23/2017. A Village pre-construction meeting is scheduled for 03/27/2017. Construction is expected to begin the week of 04/03/2017. |
March 17, 2017 | A pre-construction meeting has been scheduled with IDOT for 03/23/2017 and a Village pre-construction meeting is scheduled for 03/27/2017. |
March 3, 2017 | IDOT is attempting to schedule a pre-construction meeting for late March. |
February 10, 2017 | The Village is waiting for IDOT to award a contract and schedule a pre-construction meeting. |
January 27, 2017 | Bids were opened and K-Five was the apparent low bidder. The Village has given its concurrence to IDOT to award a contract to K-Five, the low bidder. |
December 23, 2016 | This project is on the IDOT letting for 01/20/2017. |
December 2, 2016 | IDOT submitted funding agreements and Phase III engineering agreements to Staff. Staff will present the agreements to the Board for consideration at the 12/19/2016 Board Meeting. |
November 4, 2016 | Final Phase II plans and specs were submitted to IDOT on 10/28/2016. |
October 21, 2016 | Phase II plans and specs were submitted to IDOT on 10/17/2016. |
October 14, 2016 | Staff has reviewed Phase II plans and specs and they will be submitted to IDOT on 10/17/2016. |
September 30, 2016 | The PESA report was completed by the environmental engineers. |
August 19, 2016 | Pre-final plans were submitted to IDOT on 08/19/2016. |
August 12, 2016 | Pre-final plans will be submitted to IDOT on 08/19/2016. |
March 4, 2016 | Engineering consultant Clark Dietz is working on the Phase II design engineering of the project. |
February 12, 2016 | Staff held a kick-off meeting with Clark Dietz for the Phase II design engineering of the project. A meeting with IDOT has also been scheduled for 02/17/2016. |
January 29, 2016 | The Phase II Engineering Proposal from Clark Dietz was approved by the Board at the 01/25/2016 board meeting. |
January 22, 2016 | Staff has submitted a Phase II Engineering Proposal from Clark Dietz to be considered by the Board at the 01/25/2016 Board Meeting. |
October 16, 2015 | Staff learned this week that the additional STP funding requested for this project in August will be recommended for award. |
August 7, 2015 | Staff submitted an updated grant application this week for STP funding for this project. The grant, if awarded, would provide additional funding for construction and would also include funding for Phase III construction engineering, which was not previously eligible. |
July 10, 2015 | Staff expects to submit an updated STP grant application which would include a request for funding for Phase III construction engineering in addition to the construction funding already awarded. |
March 6, 2015 | This project has been approved for $489,135 federal Surface Transportation Program (STP) funding, out of a total estimated construction cost of $698,766. The project has been added to the draft five-year capital improvement program. |
Contact Us
-
Michael Guerra, P.E.
Public Works Director
Email the Engineering Division
Online Contact Form
Staff Directory
Office Address
Public Works Department
11 West Home Avenue
Villa Park, Illinois 60181
Mailing Address
Public Works Department
20 South Ardmore Avenue
Villa Park, Illinois 60181
Ph: 630-834-8505
Fx: 630-834-8509
Emergency: 630-834-7447
Hours
Monday through Friday
7:30 a.m. to 4:00 p.m.