Route 83 Lift Station

Description

This Project consists of the replacement of as existing sanitary lift station including demolition of various surface amenities including the tops of the existing wet well as well as the associated piping and pumps to 20 feet below grade, replacing with submersible pumps, electronic controls, and piping; tying into the existing Supervisory Control and Data Acquisition (SCADA) system and all other modifications necessary to have a fully operating lift station. The lift station is located south of the intersection of Saint Charles Road and Route 83 on the west side of Route 83 near the dead-end of South Riverside Court in the Village of Villa Park, Illinois.

Bidding Documents

Planholders

OrganizationOrganization Address
Marc Kresmery1725 Weld Road
Elgin, IL 60123
Flow-Technics181 Ontario Street
Frankfort, IL 60423
Berger Excavating1205 Garland Road
Wauconda, IL 60084
H. Linden & Sons722 E. South Street Unit D
Plano, IL 60545
Bolder Contractors316 Cary Point Drive
Cary, IL 60013
Bid Tool14205 N. Mopac, Suite 550
Austin, TX 78728
John Neri Construction Company770 W. Factory Road
Addison, IL 60101
Landmark Environmental Systems1813 N. Mill Street
Naperville, IL 60563
Dimeo Brothers720 Richard Lane
Elk Grove, IL 60007
Sheridan Plumbing and Sewer6754 W. 74th Street
Bedford Park, IL 60638


Project Updates

Posted DateDescription
March 4, 2016Project is closed out.
May 29, 2015A punch list inspection meeting was held on 05/22/2015. The contractor is now working to complete this punch list work. Staff also processed a pay request this week.
May 22, 2015A punch list inspection is scheduled 05/22/2015.
May 15, 2015A punch list inspection is scheduled for next week.
May 1, 2015The lift station was started up this week following replacement of the pumps. Some work pertaining to the control and electrical systems still remains.
April 10, 2015Construction for this project is underway. The control cabinet and concrete pad were installed this week, along with most of the electrical conduits.
April 3, 2015Construction for this project is underway. It is expected that work is to be completed prior to 05/01/2015.
March 6, 2015A pre-construction meeting has been held. It is expected that work is to be completed prior to 05/01/2015.
October 24, 2014This project was advertised for bidding, today, 10/24/2014. Staff completed preparation of the bid manual for the project this week.