- Home
- Government
- Departments
- Public Works Department
- Engineering Division
- Construction Projects
- Completed Projects
- Completed Projects 2014
- Northwest Area Sewer Rehabilitation Program
Northwest Area Sewer Rehabilitation Program
Objective
To significantly improve the condition of selected sanitary sewer mains throughout the Village.
Description
This program consists of the rehabilitation of existing sewers by utilizing point repairs and sewer lining in the "Northwest" area of the Village: the area bounded by North Avenue on the north, Sunset Drive on the south, Lincoln Avenue on the west and Westmore Avenue on the east. The program will include approximately 6,100 lineal feet of sewer lining with pipe diameters ranging from 8 inches to 10 inches, and will also include approximately 10 point repairs.
Justification
The improvements are identified in the Sanitary Sewer Master Plan dated February 2008. The rehabilitation efforts will reduce the inflow and infiltration (I/I) of both stormwater and debris into the sanitary sewer system, thus lessening both the frequency and severity of sewer surcharges and sewer backups. The life of the existing sewer will also be extended. The Village will receive funding from the Community Development Block Grant (CDBG) Program for approximately 75% of construction costs.
Bidding Documents
Project Documents
Project Updates
Posted Date | Description |
---|---|
February 20, 2015 | DuPage County has issued final approval of this project. Staff is awaiting a final reimbursement payment from the county. |
February 6, 2015 | Staff has submitted final documents to DuPage County for grant close-out. |
January 23, 2015 | Staff submitted a final grant reimbursement request for this project this week. |
January 16, 2015 | Construction of this project is complete. Staff processed final payment to the contractor this week. |
January 9, 2015 | Construction of this project is complete. Staff submitted a partial grant reimbursement request last week. |
December 19, 2014 | A final change order for this project has been approved. Construction is substantially complete. Punch list work has been completed but must still be inspected. Staff is working to complete various tasks related to grant administration. |
December 12, 2014 | A final change order for this project was approved this week. |
December 5, 2014 | Staff has submitted a final change order for this project for consideration at the 12/08/2014 Village Board meeting. |
November 21, 2014 | Staff has obtained contractor approval of a final change order for this project. |
November 14, 2014 | Staff worked this week to prepare a final change order for this project. Some punch list work remains, and is expected to be completed in the next one to two weeks. Staff is working to complete various tasks related to grant administration. |
October 24, 2014 | Construction of this project is substantially complete. Sanitary sewer main lining, point repairs and T-liner installation are finished. Some punch list work remains, and is expected to be completed in the next two to three weeks. Staff is working to complete various tasks related to grant administration. |
October 17, 2014 | Installation of T-liners has begun, and is expected to be completed next week. Staff is working to complete various tasks related to grant administration. |
September 26, 2014 | Construction of this project continued this week. Sanitary sewer main lining is complete. Two point repairs have been completed. Installation of T-liners must still take place. Staff is working to complete various tasks related to grant administration. |
September 19, 2014 | Construction of this project continued this week. Sanitary sewer lining is currently in progress. Installation of T-liners must still take place. Staff is working to complete various tasks related to grant administration. |
September 12, 2014 | Construction of this project continued this week. Sanitary sewer lining is currently in progress. Installation of T-liners must still take place. Staff is working to complete various tasks related to grant administration. |
September 5, 2014 | Construction of this project continued this week. Sanitary sewer lining is currently in progress. Two point repairs have been completed the week of 09/01/2014. Staff is working to complete various tasks related to grant administration. |
August 29, 2014 | Construction of this project continued this week. Sanitary sewer lining is currently in progress. Staff is working to complete various tasks related to grant administration. |
August 22, 2014 | Construction of this project continued this week. Sanitary sewer televising and cleaning are currently in progress. Staff is working to complete various tasks related to grant administration. |
August 15, 2014 | Construction of this project began this week. Sanitary sewer televising is currently in progress. |
August 8, 2014 | Staff held a pre-construction meeting for this project on 08/06/2014. Staff is awaiting the return of signed contracts from the prospective contractor and is working to complete various tasks related to grant administration. |
July 11, 2014 | Staff prepared a recommendation this week to award a contract for this program to the low bidder, Visu-Sewer of Illinois, LLC, or Bridgeview, Illinois, in the amount of $226,676.25. Staff submitted this recommendation for consideration by the Village Board at the 07/14/2014 Village Board meeting. Staff is working to complete various tasks related to contract award and grant administration. |
July 4, 2014 | Staff held a bid opening for this project this week. The apparent low bidder is Visu-Sewer of Illinois, LLC, of Bridgeview, Illinois, with a bid of $226,676.25. Staff is working to complete various tasks related to bidding and the grant for this project. |
June 20, 2014 | This project is currently advertised for bidding. Staff has scheduled a mandatory pre-bid meeting for 06/24/2014. Staff is distributing and responding to inquiries from potential bidders and other interested parties. |
June 13, 2014 | This project was advertised for bidding, today, 06/13/2014. Staff completed preparation of the bid manual for the project this week. |
June 6, 2014 | Staff completed preparation of a draft bid manual for this project and submitted it to the DuPage County CDC for review this week. The project is tentatively scheduled to be advertised for bidding in mid-June. |
May 30, 2014 | Engineering design of this project was completed and submitted to the Village this week by engineering consultant RJN Group. Village staff is now working to complete the preparation of the bid manual for this project, at which point it will be submitted to the DuPage County CDC for review. |
May 16,2014 | Surveying of areas where point repairs are to be completed is now finished. Engineering consultant RJN Group is nearing completion of their design. |
May 9, 2014 | Surveying of areas where point repairs are to be completed began this week. |
April 18, 2014 | Staff made a site visit this week to review the locations of proposed point repairs. |
April 4, 2014 | Staff held a CDBG grant kick-off meeting with the DuPage County CDC on 02/25/2014. The next step in the design process is to perform some surveying of areas where point repairs are to be completed. This surveying work is expected to take place when the weather becomes favorable. |
Contact Us
-
Michael Guerra, P.E.
Public Works Director
Email the Engineering Division
Online Contact Form
Staff Directory
Office Address
Public Works Department
11 West Home Avenue
Villa Park, Illinois 60181
Mailing Address
Public Works Department
20 South Ardmore Avenue
Villa Park, Illinois 60181
Ph: 630-834-8505
Fx: 630-834-8509
Emergency: 630-834-7447
Hours
Monday through Friday
7:30 a.m. to 4:00 p.m.