East Park Boulevard Improvement Project

General Information

Project Location(s):Park Boulevard - Villa Avenue to the east dead end
Project Status:Under Construction
Start Date:February 15, 2015
Tentative Completion Date:To Be Determined
Contractor:A Lamp Concrete Contractors, Inc.
Construction Engineer:Clark Dietz, Inc.
Design Engineer:Robinson Engineering
Awarded Contract Amount:$1,397,533.16
Funding Sources:Street Improvement; GO Bonds; Water Supply; Wastewater

Objective

To significantly improve the condition of the roadway by removing the existing deteriorated pavement and replacing it with new, structurally sound pavement. The storm sewer installation will lessen the frequency of flooding since roadway drainage will no longer be connected to the combined sewer system.

Description

This project consists of the complete reconstruction of East Park Boulevard from Villa Avenue to the east dead end, and includes new storm sewer installation, as well as selective improvements to the sanitary sewer and water supply systems.

Justification

The Village's pavement management program has determined that the condition of the street has deteriorated to the point where complete reconstruction is needed. The storm sewer, which is recommended in a 1981 Flood Control Study, will lessen the frequency of combined sewer surcharging. Construction is contingent upon the availability of funding.

Bidding Documents

Contract

Project Documents

Project Updates

Posted DateDescription
November 25, 2016Upon completion of the entire punch list staff will work to close out the project.
July 22, 2016All that remains are punch list items and project closeout.
July 15, 2016The asphalt surface was installed. All that remains are punch list items.
July 8, 2016Final surface paving is expected to take place in the next one to two weeks.
June 17, 2016Parkway restoration has been completed.
June 10, 2016Parkway restoration has begun.
June 3, 2016Adjustment of roadway structures has begun.
May 27, 2016HMA binder course has been installed. Parkway grading has begun.
May 6, 2016Concrete work on the south side has been completed. Work the north side is tentatively scheduled to commence next week.
April 29, 2016All underground work has been completed. Removal of the curb on the south side has begun.
April 15, 2016Directional boring of the sewer under the Prairie Path is complete and all remaining storm mains should be complete next week.
April 8, 2016Directional boring of the sewer under the Prairie Path has begun. Water services continue to be replaced.
April 1, 2016All water main improvement has been completed and work continues on water service replacement. Residents will be notified prior to water being shut off.
March 25, 2016The contractor has begun water system improvements. Water may be shutoff at various times to allow for this work to be completed. Residents will be notified prior to water begin shut off.
March 18, 2016Construction of the storm sewer continues working west.
March 11, 2016Installation of the new storm sewer continues. All water improvements that require Saturday water shutoffs have been completed.
March 4, 2016Construction of the storm sewer is nearly complete from the east end of Park Boulevard to the east side of Monterey Avenue. A water shutdown will be performed on 03/05/2016. This work is being performed on Saturday so the Montessori School does not lost water. All schools are required to have water in order to operate.
February 26, 2016Construction of the storm sewer at the east end continues.
February 19, 2016A Lamp has started construction of the storm sewer at the east end of Park Boulevard. Installation of the storm sewer is expected to continue until its completion at which time road improvements can begin.
February 5, 2016An onsite meeting was held this week with the Contractor and construction is currently scheduled to begin the week of 02/15/2016.
December 4, 2015A preconstruction meeting was held on 12/02/2015. Construction is currently scheduled to start 03/01/2016 weather permitting.
November 27, 2015A preconstruction meeting has been scheduled for 12/02/2015.
November 20, 2015Staff is working to execute contracts and set up a preconstruction meeting. Staff is also in the process of televising building sewer service lines in the project area, with 32 properties televised to date.
November 13, 2015A contract for this project was awarded to A Lamp Concrete Contractors, Inc., of Schaumburg, Illinois, in the amount of $1,397,533.16 at the 11/09/2015 Village Board Meeting. Staff is now working to execute contracts.
October 30, 2015A bid opening for this project was held on 10/29/2015. The apparent low bidder was A Lamp Concrete Contractors, Inc., of Schaumburg, Illinois, with an as-read bid amount of $1,397,533.16. Staff is in the process of reviewing and confirming the bids. Staff is also in the process of televising building sewer service lines in the project area, with 30 properties televised to date.
October 16, 2015The bid opening has been re-scheduled for 10/29/2015. The easement agreement with the Montessori Children's Academy (MCA) granting as easement for the proposed storm sewer was approved at the 09/28/2015 Village Board meeting.
October 9, 2015Staff is in the process of televising building sewer service lines in the project area, with 30 properties televised to date.
October 2, 2015This project was advertised for bidding this week. A bid opening is scheduled for 10/20/2015. Staff is now working to completes tasks related to the bidding process.
September 25, 2015Staff has received signed easement agreements from the Montessori Children's Academy (MCA) granting an easement for the proposed storm sewer. The easement agreement has been submitted for consideration at the 09/28/2015 Village Board meeting. Staff is in the process of televising building sewer service lines in the project area with 1 property televised this week and 28 properties televised to date.
September 18, 2015Staff is in the process of televising building sewer service lines in the project area.
September 11, 2015Staff is in the process of televising building sewer services lines in the project area, with 1 property televised this week and 27 properties televised to date.
September 4, 2015Staff is in the process of televising building sewer service lines in the project area, with 1 property televised this week and 26 properties televised to date.
August 28, 2015Staff has completed its review of pre-final plans, specifications and estimates and provided engineering consultant Robinson Engineering with review comments. Staff has provided the Montessori Children's Academy (MCA) with draft documents granting an easement for the proposed storm sewer. The easement documents were revised to address feedback from MCA regarding a previous draft. Staff is in the process of televising building sewer service lines in the project area, with 2 properties televised this week and 24 properties televised to date.
August 21, 2015Staff has provided Montessori Children's Academy (MCA) with draft documents granting an easement for the proposed storm sewer. Staff has received some feedback from MCA regarding the proposed easement and is now working to address that feedback. Staff is in the process of televising building sewer service lines in the project area, with 1 property televised this week and 14 properties televised to date.
August 14, 2015Staff is in the process of televising building sewer service lines in the project area, with 2 properties televised this week and 13 properties televised to date.
August 7, 2015Staff is in the process of televising building sewer service lines in the project area, with 1 property televised this week and 11 properties televised to date.
July 31, 2015Staff has received some feedback from MCA regarding the proposed easement and is now working to address that feedback. Staff is in the process of televising building sewer service lines in the project area, with 1 property televised this week and 10 properties televised to date.
July 24, 2015Staff has provided the Montessori Children's Academy (MCA) with draft documents granting an easement for the proposed storm sewer. Staff is in the process of televising building sewer service lines in the project areas, with 3 properties televised this week and 5 properties televised to date.
July 17, 2015Staff continued to work this week to complete tasks related to the Village's request for an easement from the Montessori Children's Academy (MCA) for the proposed storm sewer.
July 10, 2015Staff sent letters this week to residents in the project area with an offer to televise building sewer service lines.
July 3, 2015Staff continued to work this week to complete tasks related to the Village's request for an easement from the Montessori Children's Academy (MCA) for the proposed storm sewer.
June 26, 2015Staff continued to work this week to complete tasks related to the Village's request for an easement from the Montessori Children's Academy (MCA) for the proposed storm sewer.
June 19, 2015Staff coordinated with the Montessori Children's Academy (MCA) this week regarding the Village's request for an easement for the proposed storm sewer.
May 8, 2015Staff held a progress meeting with engineering consultant Robinson Engineering this week. The consultant is working to make revisions to the project plans.
May 1, 2015Staff received some stormwater analysis information from engineering consultant Robinson Engineering this week.
April 24, 2015Staff provided engineering consultant Robinson Engineering with some additional information pertaining to Phase II design of this project.
April 17, 2015Staff is awaiting revised documents from Robinson Engineering for the easement with the Montessori Children's Academy (MCA).
April 10, 2015Staff continued to work with engineering consultant Robinson Engineering this week to refine the documents for the easement with the Montessori Children's Academy (MCA).
April 3, 2015Staff met with the Montessori Children's Academy this week to discuss project issues and the Village's request for an easement for the proposed storm sewer. Staff has completed its review of pre-final plans, specifications and estimates, and has provided comments to engineering consultant Robinson Engineering.
March 20, 2015Staff is working to review pre-final plans, specifications and estimates. Staff has made several site visits this week to facilitate that review.
March 6, 2015Village staff has incorporated the latest project cost estimate into the proposed budget. A funding source for the new storm sewer (combined sewer separation) still needs to be determined. New language for the portion of the storm sewer crossing the Montessori School has been prepared and reviewed. Staff will be presenting the easement agreement to the property owners.
February 6, 2015Staff contacted several residents within the project area regarding possible storm sewer stub installation for future rear yard drainage systems.
November 14, 2014Staff is working with engineering consultant Robinson Engineering to complete Phase II design engineering of this project. Staff is awaiting easement documents from the consultant which will allow construction to take place on the Montessori School property.
November 7, 2014Staff held a meeting this week with the Montessori School on Park Boulevard to discuss site access issues.
October 31, 2014Staff has scheduled a meeting with the Montessori School on Park Boulevard to discuss site access issues.
August 8, 2014Staff is working with engineering consultant Robinson Engineering to complete Phase II design engineering of this project. Staff held a progress meeting with the consultant this week.
May 2, 2014Sewer televising efforts were completed this week. Staff has also received the results of some additional geotechnical investigation which took place. Staff held a progress meeting this week with engineering consultant Robinson Engineering, and is working with the consultant to complete engineering design of this project.
April 18, 2014Sewer televising efforts began this week, and will continue into next week.
April 4, 2014Staff is working with engineering consultant Robinson Engineering to complete engineering design of this project. Staff has obtained approval of purchase orders for sewer televising and geotechnical investigation, and is now waiting for these additional efforts to take place.


Planholders

OrganizationOrganization Address
Bolder Contractors, Inc.316 Cary Point Drive
Cary, IL 60013
K-Five Construction13769 Main Street
Lemont, IL 60439
J. Congdon Sewer170 Alexandra Suite A
Carol Stream, IL 60188
A Lamp Concrete1900 Wright
Schaumburg, IL 60193
DiMeo Brothers720 Richard Lane
Elk Grove Village, IL 60007
Martam Construction1200 Gasket Drive
Elgin, IL 60120
Archon Construction563 S. Route 53
Addison, IL 60101
Gerardi Sewer & Water Co.4520 N. Osage Avenue
Norridge, IL 60706
Chicagoland Paving2250 Telser Road
Lake Zurich, IL 60047
Alliance Contractors1166 Lake Avenue
Woodstock, IL 60098
Landmark11916 W. Main Street
Huntley, IL 60142
Brothers Asphalt315 S. Stewart
Addison, IL 60101
Orange Crush321 Center Street
Hillside, IL 60162
M&J Asphalt3124 S. 60th Court
Cicero, IL 60804
John Neri Construction Company Inc.770 Factory Road
Addison, IL 60101
Berger Excavating1205 N. Garland Road
Wauconda, IL 60084
Swallow Construction4250 Lacey
Downers Grove, IL 60515
JS Riemer16N158 Tyrrell Road
Elgin, IL 60124
Acqua40 E. Chicago Avenue Suite 138
Chicago, IL 60611
H. Linden & Sons Sewer & Water722 E. South Street Unit D
Plano, IL 60545
Arrow Road3401 S. Busse
Mount Prospect, IL 60056
Schroeder11022 S. Grant Highway
Huntley, IL 60152


Not For Bid Planholders

OrganizationOrganization Address
Trine Construction Corp.27W364 North Avenue
West Chicago, IL 60185
Western Utility2565 Palmer Avenue
University Park, IL 60484
Elmhurst Chicago Stone Company400 West First Street
Elmhurst, IL 60126
  1. 1
  2. 2
  3. 3
  4. 4
  5. 5