Yale Avenue Improvement Project

General Information

Project Location(s):
North Yale Avenue from Plymouth to Ridge
Project Status:
Design
Bid Opening Date:
TBD
Construction Start Date:
TBD
Construction Completion Date:
2020
Contractor:
TBD
Construction Engineer:
TBD
Design Engineer:
Baxter & Woodman, Inc.
Awarded Contract Amount:
TBD
Adjusted Final Contract Amount:
TBD
Funding Source(s):
GO Bonds, Water Supply Fund, Wastewater Fund, GDBG Grant

Objective

To improve the condition of the roadway by removing the existing deteriorated pavement and replacing it with a new, structurally sound pavement. To improve water system capacity and reliability by replacing the existing water main.

Description

This project consists of the reconstruction of North Yale Avenue from Plymouth Street to Ridge Road. The project includes replacement of the existing water main. Some selective sanitary sewer system improvements are also included.

Justification

The Village's pavement management program has determined that the condition of the street has deteriorated to the point that pavement rehabilitation is needed. This project is to be partially funded by voter approved bond proceeds. The Village plans to apply for grant funding under the Community Development Block Grant (CDBG) Program for the water main improvements.

Bidding Documents

Contract Documents

Related Documents

PLANHOLDERS

OrganizationOrganization Address
None at this time

Project Updates

Date
Description
May 10, 2019An engineering design kick-off meeting was held with the design consultant this week. Topographic survey is complete. Staff is working to complete the required CCDD testing and analysis.
May 3, 2019Topographic survey was completed this week. Staff is working to complete the required CCDD testing and analysis.
April 22, 2019An engineering agreement with Baxter & Woodman, Inc. of Crystal Lake, Illinois was approved by the Village Board at the Monday, April 22, 2019 Village Board Meeting for design engineering services.