- Home
- Government
- Departments
- Public Works Department
- Engineering Division
- Construction Projects
- Active Projects
- Maple Area Improvement Project
Maple Area Improvement Project
General Information
Project Location(s): | Various (see map) |
---|---|
Project Status: | Design |
Bid Opening Date: | TBD |
Construction Start Date: | TBD |
Construction Completion Date: | TBD |
Contractor: | TBD |
Construction Engineer: | TBD |
Design Engineer: | Edwin Hancock Engineering Company |
Awarded Contract Amount: | TBD |
Adjusted Final Contract Amount: | TBD |
Funding Source(s): | Street Improvement Fund, GO Bonds, Water Supply Fund, Wastewater Fund, Sewer Separation Fund |
Objective
To improve the area of the roadway by removing the existing deteriorated pavement and replacing it with new, structurally sound pavement. To reduce the frequency and severity of flooding and sewer backups by separating the existing combined sewer.
Description
This project consists of the reconstruction of selected areas on East Maple Ave, North Summit Ave, East Oak St, East Pine St, East Division St, and North Myrtle Ave within the Village of Villa Park. The project includes combined sewer separation. Some selective water and sanitary sewer system improvements are also included.
Justification
The Village's pavement management program has determined that the condition of these streets has deteriorated to the point that pavement rehabilitation is needed. This project is to be partially funded by voter approved bond proceeds.
Bidding Documents
Contract Documents
Planholders
Organization | Organization Address |
---|---|
None at this time |
Project Updates
Date | Description |
---|---|
January 1, 2021 | Plans for this project are now final, pending IEPA review. A loan ordinance authorizing the Village to borrow funds was approved at the September 14, 2020 Village Board meeting. The loan ordinance public comment period has expired, and staff is proceeding with preparation of the final application to the IEPA. |
December 4, 2020 | Staff is proceeding with preparation of the final application to the IEPA. |
October 30, 2020 | Plans for this project are now final, pending IEPA review. A loan ordinance authorizing the Village to borrow funds from the Illinois EPA was approved at the September 14, 2020 Village Board meeting. The loan ordinance is in a public comment period has expired with no comments so staff is preparing the final application for the IEPA. |
October 9, 2020 | The loan ordinance is in a public comment period that extends through October 24, 2020. |
October 2, 2020 | Plans for this project are now final, pending IEPA review. A loan ordinance authorizing the Village to borrow funds from the Illinois EPA was approved at the September 14, 2020 Village Board meeting. The ordinance is now subject to a required public comment period. |
August 28, 2020 | Staff has received pre-final plans. The design engineer is now working to complete final plans and specifications. Staff is also working with the design engineer to finalize the IEPA loan application for the project. A loan ordinance authorizing the Village to borrow funds from the Illinois EPA will be submitted for consideration at an upcoming Village Board meeting. |
July 10, 2020 | Staff has received pre-final plans. The design engineer is now working to complete final plans and specifications. Staff is also working with the design engineer to finalize the IEPA loan application for the project in July. |
July 3, 2020 | The design engineer is now working to complete final plans and specifications. Staff is also working with the design engineer to finalize the IEPA loan application for the project in July. |
June 26, 2020 | Staff has received pre-final plans. The design engineer is now working to complete final plans and specifications. Staff is also working with the design engineer to finalize the IEPA loan application for the project. |
May 1, 2020 | The design engineer is working to complete pre-final plans and specifications. |
April 3, 2020 | The design engineer is working to complete pre-final plans and specifications. |
March 13, 2020 | Staff has received preliminary plans. The design engineer is now working to complete pre-final plans and specifications. |
February 21, 2020 | The engineer is working to make necessary revisions to the review comments. |
December 13, 2019 | Staff has reviewed the preliminary design plans submitted by the design engineer and provided the design engineer with review comments. |
December 2, 2019 | The first set of Sewer Service Televising letters have been sent to residents located on or near E Pine St within the project area. |
November 22, 2019 | The design engineer has submitted preliminary design plans. Staff reviewed those plans and provided the design engineer with review comments this week. |
November 15, 2019 | Staff has held a progress meeting with the design engineer. The design engineer has submitted preliminary design plans. Staff is in the process of reviewing those plans and expects to provide the design engineer with review comments in the next one to two weeks. |
October 11, 2019 | The design engineer has submitted preliminary design plans. Staff is in the process of reviewing those plans. |
July 11, 2019 | The design engineer has submitted preliminary design plans. Staff is in the process of reviewing those plans. |
June 28, 2019 | This project is currently under design. Preliminary plans are expected to be submitted for review in the next two weeks. |
April 18, 2019 | This project is currently under design. Staff held a progress meeting with the design consultant this week. Preliminary plans are expected to be submitted for review in June. |
December 13, 2018 | Design of the project is ongoing. |
October 5, 2018 | A letter was sent to residents within the project area notifying them of ongoing survey work for the project. |
Contact Us
-
Michael Guerra, P.E.
Public Works Director
Email the Engineering Division
Online Contact Form
Staff Directory
Office Address
Public Works Department
11 West Home Avenue
Villa Park, Illinois 60181
Mailing Address
Public Works Department
20 South Ardmore Avenue
Villa Park, Illinois 60181
Ph: 630-834-8505
Fx: 630-834-8509
Emergency: 630-834-7447
Hours
Monday through Friday
7:30 a.m. to 4:00 p.m.