General Information
Project Location(s): | Addison Avenue - Madison to Washington Madison Street - Addison to Michigan Wisconsin Avenue - Jackson to Washington |
---|---|
Project Status: | Design |
Bid Opening Date: | TBD |
Mandatory Pre Bid Meeting: | TBD |
QuestCDN Number: | TBD |
Construction Start Date: | 2023-2024 |
Construction Completion Date: | TBD |
Contractor: | TBD |
Construction Engineer: | TBD |
Design Engineer: | V3 Companies of Illinois, Ltd. |
Awarded Contract Amount: | TBD |
Adjusted Final Contract Amount: | TBD |
Funding Source(s): | Street Referendum, Wastewater Fund |
This project is a portion of the larger Sugar Creek Watershed Drainage Improvement Project. This project includes:
- Michigan Avenue Improvement Project (Madison to Jackson) (2018)
- Jackson Pond Overflow Project (2019)
- Jackson Pond Outlet Project (2019)
- Jackson Pond Expansion Project (2022)
- Jackson Area Improvement Project (2023)
Objective
To reduce the likelihood of flooding during storm events by separating and expanding the storm sewer system. To improve the condition of the roadway by means of selected pavement rehabilitation methods.
Description
This project consists of roadway improvements on Addison Avenue from Madison Street to Washington Street, Wisconsin Avenue from Jackson Street to Washington Street, and Madison Street from Addison Avenue to Michigan Avenue. The project includes the installation of storm sewers. Some selective water system and sanitary sewer system improvements are also included.
Justification
The sewer separation and storm sewer installation will reduce the likelihood of flooding in the area. The Village's pavement management program has determined that the condition of the streets have deteriorated to the point that pavement rehabilitation is needed. This project is to be partially funded by voter approved bond proceeds.
Bidding & Planholders Information
Village Projects are typically bid through the online bidding service QuestCDN. A list of plan holders as well as the initial bid tabulation will be available on the project page. For more details on how the Village bidding process works, please visit the Bidding Information page.
Bidding Documents
Contract Documents
Related Documents
Project Updates
Date | Description |
---|---|
October 28, 2022 | Staff is in the process of reviewing plans and specifications and has held several design progress meetings. Bidding is currently expected to take place in late 2022 or early 2023. |
October 7, 2022 | Geotechnical investigation field work for this phase was performed earlier this month. Staff is in the process of reviewing plans and specifications, and has held several design progress meetings. This phase will be advertised for bidding when design is complete. Bidding is currently expected to take place in late 2022 or early 2023. |
April 1, 2022 | This project is currently under design. |
Contact Us
-
Michael Guerra, P.E.
Public Works Director
Email the Engineering Division
Online Contact Form
Staff Directory
Office Address
Public Works Department
11 West Home Avenue
Villa Park, Illinois 60181
Mailing Address
Public Works Department
20 South Ardmore Avenue
Villa Park, Illinois 60181
Ph: 630-834-8505
Fx: 630-834-8509
Emergency: 630-834-7447
Hours
Monday through Friday
7:30 a.m. to 4:00 p.m.