Rebuild IL Resurfacing Project

General Information

Project Location(s):
Division St - Westmore to Addison
Elm St - Westmore to Addison
Wisconsin Ave - St. Charles to Division
Project Status:
Bidding
Bid Opening Date:
September 2, 2022, at 10:00 a.m. CST.
Mandatory Pre Bid Meeting:
N/A
QuestCDN Number:
8271001
Construction Start Date:
2022
Construction Completion Date:
2022
Contractor:
TBD
Construction Engineer:
TBD
Design Engineer:
TranSystems Corp.
Awarded Contract Amount:
TBD
Adjusted Final Contract Amount:
TBD
Funding Source(s):
REBUILD Illinois

Objective

This project consists of the resurfacing of various streets throughout the village.

Description

This project will consist of a mill and overlay of the above roadways.  It also includes any necessary road subgrade patching, structure adjustments or reconstruction, curb ramp improvements to comply with ADA requirements, and all necessary restoration work for these improvements.

Justification

The village's pavement management program has determined that these streets are in need of repair.

Bidding & Planholders  Information

Village Projects are typically bid through the online bidding service QuestCDN. A list of plan holders as well as the initial bid tabulation will be available on the project page. For more details on how the Village bidding process works, please visit the Bidding Information page.

Project Updates

Date
Description
September 2, 2022A bid opening was held today for the project. The apparent low bidder was Arrow Road Construction Company, of Elk Grove, IL. Staff is in the process of reviewing the bids and will then make a final determination.
August 18, 2022The project was advertised for bidding. The bid opening date is September 2, 2022, at 10:00 a.m.